MRP Failing with "Underlying provider failed on EnListTransaction." "The requested operation cannot be completed because the connection has been broken."

Thanks for the response, Haso. Although an upgrade may be the final solution, in the short term it may not be a viable option. Our upgrade process takes a little while :slight_smile:

After some testing in our Pilot environment and delving into the logs, we have stumbled into a specific line of the mrp log that it repeatedly fails at. It is in the portion of MRP Regen that deletes unfirm jobs, and is below:

09:59:48 Site: SITE After Delete of Table: PcValueSet for JobMtl
10:04:38 The underlying provider failed on EnlistTransaction.
10:04:38 The requested operation cannot be completed because the connection has been broken.
10:04:37 The underlying provider failed on EnlistTransaction.

We are wondering if there is a data related issue in that plant (part/routing/job). We were completing successful regens with some regularity until a few weeks to a month ago, so it seems something changed. If anybody has any ideas, we have open ears.

We have a ticket open with Epicor, so if anything comes up from that case we will post here. The help is very much appreciated.