MRP question Blank Title 58063

The receipt quantity drops to zero because none have been completed on
the job. The receipt quantity would usually equal the completed
quantity minus the received to stock quantity



Gary



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of leann_37
Sent: 24 July 2007 01:34
To: vantage@yahoogroups.com
Subject: [Vantage] Re: MRP question



According to Epicor, a job is live to scheduling and capacity until
closed- not just completed. The receipt quantity drops to 0, but it
is still considered "live" until it is closed.
Hope this helps!
- leAnn

--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Jasper Recto" <jrecto@...> wrote:
>
> Lets assume we have a SO demad for 10 pcs. MRP would create a job
for those 10 pcs.
>
> If the job is open for 10pcs and only 9 are completed, Vantage
assumes you will continue and finish the last piece.
> If we close the job short 1piece, Vantage would make a new MRP job
for 1 because there is still a demand.
>
> What whould happen if the job was just checked as completed. Does
MRP assume that no more activity will be performed on that job? What
happens to the material requirements?
> Does MRP assume that any outstanding material requirements that
were associated with the job go away?
> Will MRP create a new Job for the remaining 1 pc balance?
>
> Thanks,
> Jasper
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>





[Non-text portions of this message have been removed]
Lets assume we have a SO demad for 10 pcs. MRP would create a job for those 10 pcs.

If the job is open for 10pcs and only 9 are completed, Vantage assumes you will continue and finish the last piece.
If we close the job short 1piece, Vantage would make a new MRP job for 1 because there is still a demand.

What whould happen if the job was just checked as completed. Does MRP assume that no more activity will be performed on that job? What happens to the material requirements?
Does MRP assume that any outstanding material requirements that were associated with the job go away?
Will MRP create a new Job for the remaining 1 pc balance?

Thanks,
Jasper







[Non-text portions of this message have been removed]
According to Epicor, a job is live to scheduling and capacity until
closed- not just completed. The receipt quantity drops to 0, but it
is still considered "live" until it is closed.
Hope this helps!
- leAnn


--- In vantage@yahoogroups.com, "Jasper Recto" <jrecto@...> wrote:
>
> Lets assume we have a SO demad for 10 pcs. MRP would create a job
for those 10 pcs.
>
> If the job is open for 10pcs and only 9 are completed, Vantage
assumes you will continue and finish the last piece.
> If we close the job short 1piece, Vantage would make a new MRP job
for 1 because there is still a demand.
>
> What whould happen if the job was just checked as completed. Does
MRP assume that no more activity will be performed on that job? What
happens to the material requirements?
> Does MRP assume that any outstanding material requirements that
were associated with the job go away?
> Will MRP create a new Job for the remaining 1 pc balance?
>
> Thanks,
> Jasper
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
Jasper



Jobs clear their shopload at point of completion.



For make direct jobs the job stays linked to the order and a new job
does not get created upon run of MRP

For stock items, because upon completion the time phase uses the
completed quantity (9) as the receipt value MRP creates a new job for
balance of the demand (1)



Upon job completion the system completes all materials and operations,
hence all demand for materials and labour is removed



Gary Parfrey



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Jasper Recto
Sent: 23 July 2007 21:36
To: Vantage Groups (E-mail)
Subject: [Vantage] MRP question



Lets assume we have a SO demad for 10 pcs. MRP would create a job for
those 10 pcs.

If the job is open for 10pcs and only 9 are completed, Vantage assumes
you will continue and finish the last piece.
If we close the job short 1piece, Vantage would make a new MRP job for 1
because there is still a demand.

What whould happen if the job was just checked as completed. Does MRP
assume that no more activity will be performed on that job? What happens
to the material requirements?
Does MRP assume that any outstanding material requirements that were
associated with the job go away?
Will MRP create a new Job for the remaining 1 pc balance?

Thanks,
Jasper


[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]