Did you issue that nonstock part from inventory to the job?



Rob Bucek

Manufacturing Engineer

PH: 715-284-5376 ext 311

FAX: 715-284-4084

<http://www.dsmfg.com/>

(Click the logo to view our site)



________________________________

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of roughbros@...
Sent: Thursday, March 26, 2009 8:04 AM
To: Vantage Users
Subject: [Vantage] Non-Stock Part Vantage 8.03H





I am having an issue with a non-stock part using whatever is in standard
cost to post to CGS accounts, instead of using costs built up in a job.

In 6.1, we were able to set up Generic Parts in the part master (such as
Sheet Metal Work) as non-stock, manufactured. And once shipped it would
post all the expenses that were assigned to the applicable job to CGS
based upon the accounts in the Product Group. 8.03 does not appear to
function this way.

Basically, we want to have an item in the part master that will be
configured different ways and post the Costs to the CGS acct that are
built up in the jobs.

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]
I am having an issue with a non-stock part using whatever is in standard cost to post to CGS accounts, instead of using costs built up in a job.
Â
In 6.1, we were able to set up Generic Parts in the part master (such as Sheet Metal Work) as non-stock, manufactured. And once shipped it would post all the expenses that were assigned to the applicable job to CGS based upon the accounts in the Product Group. 8.03 does not appear to function this way.
Â
Basically, we want to have an item in the part master that will be configured different ways and post the Costs to the CGS acct that are built up in the jobs.Â




[Non-text portions of this message have been removed]