Setup: .33 hrs
Addl Setup Qty : 250
Addl SetupHours: .333 hrs
Miguel A. Santillan
Compass Manufacturing Systems
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Thursday, May 5, 2016 9:17 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Operation Set-Up Time
We are new to Epicor implementing ver 10.1.400. We are confused on how to enter set-up time for an operation. For example: Press brake has a set-up time of 20 minutes with a standard run quantity of 250 pieces. The production standard is 65 pieces per hour. How do we enter this in Operation on the Method of Manufacturing?
John Funke
LB White Co.
Disclaimer
The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or taking action in relation of the contents of this information is strictly prohibited and may be unlawful.