PartWip Table not showing some operations

,

Is there something on a job operation that would cause the Part WIP table to not show the correct operation? I am trying to show what ops are currently in process in our plant, but I have 2 operations that never show, they always show as the previous operation even after the previous op is marked complete. Once these ops are completed, it will show as the last operation, but will never show as the current op. I assume something is not set up correctly on the job, operation, or resource Group, but I cannot figure out what is wrong. The auto move is checked, they are qty only operations, but we have multiple operations on these jobs marked that way and they show up correctly. Any suggestions on what to check would be appreciated.