Planning Workbench how to only show jobs starting within the next 15 days

Hello,

Currently the list is long and the user only need to address jobs which should start within the next 2 weeks.

The start date column is not showing any data. the column TargetJobNum is showing a valid existing job. Would it be possible to have a quick search baq that could return jobs with a startdate within 2 weeks or less ?

How would I acheive this ? How to set it up? What field I can right click on to access the Quick search config?

Thank you

Pierre

I tried playing around with this, and I couldn’t get it either. But I think it may be because the planning work bench doesn’t use job as a key field. You would have to base it on order or part number, and then you lose the start date of the job. :thinking: