The Production Planning Workbench gets populated when you run the Production Planning Process under Job Management. We run MRP as a Process Set along with the Production Planning Process.
I believe the PartSug table is populated when you run MRP. You can view these suggestions via Planning Workbench.
I don’t think they correspond.
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Manasa Reddy
Sent: Wednesday, December 05, 2012 10:26 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Planning Wrkbnch / PartSug Table
Marking the Make Direct check box on the release tab on a Sales Order.
Manasa
I believe the PartSug table is populated when you run MRP. You can view these suggestions via Planning Workbench.
I don’t think they correspond.
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Manasa Reddy
Sent: Wednesday, December 05, 2012 10:26 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Planning Wrkbnch / PartSug Table
Marking the Make Direct check box on the release tab on a Sales Order.
Manasa
On Dec 5, 2012, at 11:04 AM, "Vic Drecchio" <vic.drecchio@... <mailto:vic.drecchio%40swepcotube.com> > wrote:
> How does the Planning Workbench and its corresponding table, PartSug, get
> populated?
>
> -----
> No virus found in this message.
> Checked by AVG - www.avg.com
> Version: 2012.0.2221 / Virus Database: 2634/5438 - Release Date: 12/05/12
>
> [Non-text portions of this message have been removed]
>
>
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]