Priority Dispatch Resource Group and Resource - Help Needed

I’m in the process of building a priority dispatch report in baq. I need to know where the scheduled resource group and resource come from. I thought it would be from the JobOpDtl table but that doesn’t seem to always be the case. Something else I would like to know is how and where does the job scheduler store its data?

ResourceTimeUsed

@jkane,

That was fast and got me right to where I needed to be! Thanks a ton!