Is anyone familiar with the Production Complete check box while moving a job in the Job Scheduling Board?
I have been tasked with adding this functionality into Office MES. I can't seem to isolate what is happening behind the scenes when that check box is checked. I have ran a trace and I can see all the BOs that are being called. I'm hoping there is a simpler route in order to avoid a lengthy customization. Has anyone ever tried attempting this?
Thanks,
Jeromy Scherbert
What are you looking to do? That check box will complete an operation if you check it, but no quantities, labor hours, burden etc would be applied.
Rob Bucek
Production Control Manager
D&S Manufacturing
301 E. Main St.
Black River Falls, WI 54615
715-284-5376 Ext. 311
Mobile: 715-896-3119
Visit our newly redesigned Website at www.dsmfg.com
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Friday, August 19, 2016 8:34 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Production Complete
Is anyone familiar with the Production Complete check box while moving a job in the Job Scheduling Board?
I have been tasked with adding this functionality into Office MES. I can't seem to isolate what is happening behind the scenes when that check box is checked. I have ran a trace and I can see all the BOs that are being called. I'm hoping there is a simpler route in order to avoid a lengthy customization. Has anyone ever tried attempting this?
Thanks,
Jeromy Scherbert
If changing the status of the operation is all that check box does, then that will save me a world of time. I wasn't sure if quantities, labor, etc was impacted.
Thanks Rob.