Saw there was an update to Pilot and when reviewing the What’s New I noticed that Kinetic now has the ability to have Blanket POs!! Not sure when it was released, but thought everyone would like to know as it is a common request.
I have not tried it yet, but the field is on the Part Warehouse card. It looks like you can associate a PO for the part that is used as a blanket and when running MRP, if more is needed the system will add a release to the existing PO Line.
I have worked in two different Purchasing environments both in Food and Equipment. Each environment, a Blanket PO was for a master amount and then the system would generate releases off that master amount until it was consumed. I do not see this system doing that with this update. Instead it just ties a part to a PO and generates releases off that PO. There doesn’t appear to be a way to keep track of that master amount aka Blanket PO without creating a separate sheet outside of Kinetic. Am I wrong?