Joe
You need to set up a purchase part with a BOM, then you will need to add
a subreport for the BOM Materials to the PO form, linked on the part and
part revision
Gary Parfrey.
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of josephdavidberg
Sent: 03 May 2007 19:02
To: vantage@yahoogroups.com
Subject: [Vantage] Purchuring a manufactured part or purchased part with
a BOM
Hello,
I tried searching the archive for this question, and I can't seem to
find it.
How do you list the assembly parts of the purchured part on the po? In
this instance we need to list the BOM and rev's of each part.
I've created a purchase part and manufacture part, both with a bom
associated with it. IN either case, it would print that detail. Do we
have to modify the report?
How is everyone else doing it?
Joe
[Non-text portions of this message have been removed]
You need to set up a purchase part with a BOM, then you will need to add
a subreport for the BOM Materials to the PO form, linked on the part and
part revision
Gary Parfrey.
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of josephdavidberg
Sent: 03 May 2007 19:02
To: vantage@yahoogroups.com
Subject: [Vantage] Purchuring a manufactured part or purchased part with
a BOM
Hello,
I tried searching the archive for this question, and I can't seem to
find it.
How do you list the assembly parts of the purchured part on the po? In
this instance we need to list the BOM and rev's of each part.
I've created a purchase part and manufacture part, both with a bom
associated with it. IN either case, it would print that detail. Do we
have to modify the report?
How is everyone else doing it?
Joe