Scheduling Jobs in E10 for Subcontractors

Using E10, classic.

I order three parts from one of our subcontract vendors. The vendor can machine and deliver 50 pcs per week but can only do one part per week.

Is there a way to tell Epicor that only part can be expected per 5 day work week when scheduling?

Thanks in advance!

I would think if your Subcontract Resource was set up with finite capacity, it should only be scheduled for one operation at a time. The subcontractor would have to finish one operation before it began working on the next.

I would also look at the “Concurrent Capacity” field on the Resource. I think it defaults to 0, which I assume means infinite. But if you changed that to (1), I think it would limit that resource to be scheduled on one operation at a time (not concurrent).