Where are the Load Hours coming from in the Shop Load Report?
![]()
Where are the Load Hours coming from in the Shop Load Report?
![]()
I would check the Job Tracker, Operations sheet for setup and production hours.
Also if you have access to EpicWeb, you could search for the answerbook 6132MPS - Shop Load Report Notes. It’s for an older version (V8)? but… I think most of it still applies in E10.
I haven’t looked lately. so if you find any more recent documentation, please let me know.
Have you tried erp.ShopLoad.ActualHours
Trying to see if this Load Hour values is being calculated from where? Is this the burden hours that’s already been completed on the operation?
Sorry - it’s a while since I looked at this, forget my last comment.
The only way I found to work out the actual hours a resource was scheduled to be used for was by looking in the Erp.ResourceTimeUsed table.
There is are two columns in there called load date and load hours, you need to use these to get the load values against a resource.
I had to take write an external view using the above to give the following columns
jobnum]
,[assemblyseq]
,[oprseq]
,[loaddate]
,[resourcegrpid]
,[resourceid]
,[hoursinday]
I wish I could say it was easy, but alas it was not.
And not sure if this will help with your question but here is the section for Calculating Load from the answerbook 6132MPS
Spread the load hours for each operation into the appropriate time slots, by working backward from the operation Due Date/Due Hour a day at a time, until all load hours have been applied. Production hours are applied first, then setup hours (moving backwards in time, this fits with the logical progression of the job. The assumption is that setup must be done before production.
The calculations for the load hours depend on the Load Relieved By setting in the Job Management module configuration.
Oh yes - the following gives you the numeric loaddate as a date DATEADD(day, CAST(loadday AS INT),convert(date,‘01/01/1999’, 103))
Dude! This was so helpful! Thanks for sharing