Hi all,
Is there any way to check the box " Serial Numbers Required From This Operation" mid-progress of a job?
Thanks
Hi all,
Is there any way to check the box " Serial Numbers Required From This Operation" mid-progress of a job?
Thanks
I haven’t used serial numbers, but going off of the message I have a couple thoughts:
Looks to me like it doesn’t like the fact that operations 180-220 have labor transactions with completed qty’s. Delete those (if you didn’t run the COS/WIP) and I think it should let you. If you did run the COS/WIP process, I don’t think you can do it.