Work queues working?

Does anyone have suggestions / best practices for using the work queue?

We have tried, but it only works well for processes that are the first in the sequence of jobs, beyond that it gets messy.

Any inputs, suggestions or improvements you have made would be greatly appreciated!

@awissmann , I think you will need to provide more context behind your post. What are your exact issues with Work Queue?

For the most part I believe the key issue is that operations are not being closed before physically moving to the next area and the next area takes over. The queue would then not show this job as ready.

I am looking at other posts regarding making op complete mandatory, but also wanted to know how the queue was working for others and if there are any success stories.