9.05.702 - Infinite Back Scheduling - Move & Queue Times on Subcontr

All,
 
Infinite Back Scheduling – Over Ride Material Constraints = Yes.
Move and Queue Times worked on Vantage 6.1 but doesn’t get calculated in infinite back  scheduling in 9.05.702.
I’m not sure on what version it stopped working.
Verified by: Move and Queue Times don’t show on subcontract operations on the Job Schedule Board.
 
Has anyone come up with a creative work around?
Has anyone received and implemented a One Off for this for 9.05.702?
 
All comments welcome.
 
This e-mail and any attachments may contain confidential and privileged information. If you are not the intended and/or named recipient or recipients, please notify the sender immediately by return e-mail, delete this e-mail and destroy any copies. Any dissemination or use of this information by a person other than the intended recipient or recipients is unauthorized and may be illegal. Any views or opinions expressed in this email are those of the author and do not necessarily represent those of the Specialty Screw Corporation. Warning: Although precautions have been taken to make sure no viruses are present in this email, Specialty Screw Corporation cannot accept responsibility for any loss or damage that may arise from the use of this email or attachments.

  ­­