We have a SubContract Job Operation. We created a PO and then that portion of the Job has changed and the PO has been voided.
Does anyone know how to Delete (cannot delete due to the attached voided PO) or void or close the SubContract operations?
If you have a material with the same scenario you can change the qty to zero but you cannot have zero qty on a sub contract operation!
Thanks.