Does anyone have an example of a BPM or data directive that makes the labor entry field on an operation quantity only? The default is time and quantity. We need all of our operations to be quantity only. Thank you!
We have one set on JobOper for any added rows. Set it to Q or whatever the code is. If you don’t know the code, change it to Quantity only on an operation and then do a BAQ on the JobOper table and see what it says for the operation you changed.
@juliegartner1 Welcome. If you want them always to be quantity only then you can change the BOO with a DMT run and you will not need a bpm. You can do the same for existing Job Operations.
It would be a simple set field if you wanted them all set, but did not have DMT.
I assumed you have done testing, but be aware that Quantity only had cost associated with them when I tried to use it.