Global Reschedule Hangs

Mike,

Did you find this or was it found by support? Is this common? I guess my first response would be, yes I probably do have a start date in the past, which would be part of using the Global Reschedule. Now, maybe you mean that I have a start date in the past after th Global Reschedule, which is causing the hang. Additionally, I don't want to allow scheduling before today.

Did you just make these changes to allow it to finish and then reset? Or, do you always allow scheduling before today along with started operations?

Just looking to get a better understanding.

Jeff

--- In vantage@yahoogroups.com, "Mike Anstey" <manstey@...> wrote:
>
> You probably have a job with a start date in the past or blank. We had a
> similar issue with MRP and to fix it we had to go into company
> Configuration -> Modules -> Production -> Job and in the scheduling
> group box check the "Allow Scheduling Before Today" (we also have the
> "Global Rescheduled Started Operations" checked.
>
>
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
> Of jplehr
> Sent: Monday, April 04, 2011 5:39 PM
> To: vantage@yahoogroups.com
> Subject: [Vantage] Re: Global Reschedule Hangs
>
>
>
>
>
> Richard,
>
> Thanks. Where do I set the 'Ful Logging'?
>
> Jeff
>
> --- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
> Sirow Richard <rick@> wrote:
> >
> > Some times the Global Reschedule goes into an endless loop. Run it
> with Full Logging and you will probably see an enormous log file where
> it hangs. Look at that job, and the one it says there is a conflict with
> and one usually has a problem with its method of manufacture. Once you
> have the log file, submit it to support - we are asking for a counter so
> it will time out if something goes wrong.
> >
> >
> > Thanks,
> >
> > Richard L. Sirow, President
> > 516-481-5100x106
> > www.iccparts.com
> > rick@
> >
> > On Apr 4, 2011, at 1:15 PM, jplehr wrote:
> >
> > > Vantage 8.03.408A
> > >
> > > I am trying to run a Global Reschedule. This is something we have
> run successfully before, both manually and on a schedule. We stopped the
> process for a period of time and activated the scheduled process this
> past weekend.
> > >
> > > The process from the weekend did not complete as expected and based
> on what I was seeing in the System Monitor I decided to end the process.
> I then tried to run a manual process and saw the same results. Within
> System Monitor I saw the comments... "The next job to schedule 24846".
> It never processes past this.
> > >
> > > I am trying to find out what Job is causing this to hang. I assume
> it is not 24846 since it is the "next" job, although I may be wrong in
> my thinking.
> > >
> > > Has anyone had an issue similar that might be able to help out. I
> have not submitted this to support at this time. Looking here first.
> > >
> > > Jeff
> > >
> > >
> >
> >
> >
> > [Non-text portions of this message have been removed]
> >
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
Vantage 8.03.408A

I am trying to run a Global Reschedule. This is something we have run successfully before, both manually and on a schedule. We stopped the process for a period of time and activated the scheduled process this past weekend.

The process from the weekend did not complete as expected and based on what I was seeing in the System Monitor I decided to end the process. I then tried to run a manual process and saw the same results. Within System Monitor I saw the comments... "The next job to schedule 24846". It never processes past this.

I am trying to find out what Job is causing this to hang. I assume it is not 24846 since it is the "next" job, although I may be wrong in my thinking.

Has anyone had an issue similar that might be able to help out. I have not submitted this to support at this time. Looking here first.

Jeff
Some times the Global Reschedule goes into an endless loop. Run it with Full Logging and you will probably see an enormous log file where it hangs. Look at that job, and the one it says there is a conflict with and one usually has a problem with its method of manufacture. Once you have the log file, submit it to support - we are asking for a counter so it will time out if something goes wrong.


Thanks,

Richard L. Sirow, President
516-481-5100x106
www.iccparts.com
rick@...

On Apr 4, 2011, at 1:15 PM, jplehr wrote:

> Vantage 8.03.408A
>
> I am trying to run a Global Reschedule. This is something we have run successfully before, both manually and on a schedule. We stopped the process for a period of time and activated the scheduled process this past weekend.
>
> The process from the weekend did not complete as expected and based on what I was seeing in the System Monitor I decided to end the process. I then tried to run a manual process and saw the same results. Within System Monitor I saw the comments... "The next job to schedule 24846". It never processes past this.
>
> I am trying to find out what Job is causing this to hang. I assume it is not 24846 since it is the "next" job, although I may be wrong in my thinking.
>
> Has anyone had an issue similar that might be able to help out. I have not submitted this to support at this time. Looking here first.
>
> Jeff
>
>



[Non-text portions of this message have been removed]
Richard,

Thanks. Where do I set the 'Ful Logging'?

Jeff

--- In vantage@yahoogroups.com, Sirow Richard <rick@...> wrote:
>
> Some times the Global Reschedule goes into an endless loop. Run it with Full Logging and you will probably see an enormous log file where it hangs. Look at that job, and the one it says there is a conflict with and one usually has a problem with its method of manufacture. Once you have the log file, submit it to support - we are asking for a counter so it will time out if something goes wrong.
>
>
> Thanks,
>
> Richard L. Sirow, President
> 516-481-5100x106
> www.iccparts.com
> rick@...
>
> On Apr 4, 2011, at 1:15 PM, jplehr wrote:
>
> > Vantage 8.03.408A
> >
> > I am trying to run a Global Reschedule. This is something we have run successfully before, both manually and on a schedule. We stopped the process for a period of time and activated the scheduled process this past weekend.
> >
> > The process from the weekend did not complete as expected and based on what I was seeing in the System Monitor I decided to end the process. I then tried to run a manual process and saw the same results. Within System Monitor I saw the comments... "The next job to schedule 24846". It never processes past this.
> >
> > I am trying to find out what Job is causing this to hang. I assume it is not 24846 since it is the "next" job, although I may be wrong in my thinking.
> >
> > Has anyone had an issue similar that might be able to help out. I have not submitted this to support at this time. Looking here first.
> >
> > Jeff
> >
> >
>
>
>
> [Non-text portions of this message have been removed]
>
You probably have a job with a start date in the past or blank. We had a
similar issue with MRP and to fix it we had to go into company
Configuration -> Modules -> Production -> Job and in the scheduling
group box check the "Allow Scheduling Before Today" (we also have the
"Global Rescheduled Started Operations" checked.



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of jplehr
Sent: Monday, April 04, 2011 5:39 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Global Reschedule Hangs





Richard,

Thanks. Where do I set the 'Ful Logging'?

Jeff

--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
Sirow Richard <rick@...> wrote:
>
> Some times the Global Reschedule goes into an endless loop. Run it
with Full Logging and you will probably see an enormous log file where
it hangs. Look at that job, and the one it says there is a conflict with
and one usually has a problem with its method of manufacture. Once you
have the log file, submit it to support - we are asking for a counter so
it will time out if something goes wrong.
>
>
> Thanks,
>
> Richard L. Sirow, President
> 516-481-5100x106
> www.iccparts.com
> rick@...
>
> On Apr 4, 2011, at 1:15 PM, jplehr wrote:
>
> > Vantage 8.03.408A
> >
> > I am trying to run a Global Reschedule. This is something we have
run successfully before, both manually and on a schedule. We stopped the
process for a period of time and activated the scheduled process this
past weekend.
> >
> > The process from the weekend did not complete as expected and based
on what I was seeing in the System Monitor I decided to end the process.
I then tried to run a manual process and saw the same results. Within
System Monitor I saw the comments... "The next job to schedule 24846".
It never processes past this.
> >
> > I am trying to find out what Job is causing this to hang. I assume
it is not 24846 since it is the "next" job, although I may be wrong in
my thinking.
> >
> > Has anyone had an issue similar that might be able to help out. I
have not submitted this to support at this time. Looking here first.
> >
> > Jeff
> >
> >
>
>
>
> [Non-text portions of this message have been removed]
>





[Non-text portions of this message have been removed]