I believe if you're required date is in the past, and, you do not allow
historical dates, that it should end up forward scheduling from the
current date (if it isn't broke at your patch level). If you want, I
have a copy of the global scheduling technical guide available from
Epicor (its online somewhere in epicweb), but I could expedite it to you
if needed.
Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-0590
FAX: (715)284-4084
<http://www.dsmfg.com/>
(Click the logo to view our site) <http://www.dsmfg.com/>
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of jplehr
Sent: Tuesday, April 05, 2011 12:03 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Global Reschedule (Foward or Backward)
Now the question is...
What date is the Global Reschedule working to?
When you create a Job and schedule it, the system is working off the
'Required Date' as it begins the backward schedule process. Based on my
Company Configuration (not allowing scheduling before today) the system
will forward schedule when it reaches today. During the Global
Scheduling process my 'Required Date' could be in the past.
So, what is the system backward scheduling from?
Jeff
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"jplehr" <jlehr@...> wrote:
It looks like it try's to backward schedule and if it cannot meet the
date it forward schedules. Note, I do not allow scheduling before today
or started operations.
historical dates, that it should end up forward scheduling from the
current date (if it isn't broke at your patch level). If you want, I
have a copy of the global scheduling technical guide available from
Epicor (its online somewhere in epicweb), but I could expedite it to you
if needed.
Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-0590
FAX: (715)284-4084
<http://www.dsmfg.com/>
(Click the logo to view our site) <http://www.dsmfg.com/>
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of jplehr
Sent: Tuesday, April 05, 2011 12:03 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Global Reschedule (Foward or Backward)
Now the question is...
What date is the Global Reschedule working to?
When you create a Job and schedule it, the system is working off the
'Required Date' as it begins the backward schedule process. Based on my
Company Configuration (not allowing scheduling before today) the system
will forward schedule when it reaches today. During the Global
Scheduling process my 'Required Date' could be in the past.
So, what is the system backward scheduling from?
Jeff
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"jplehr" <jlehr@...> wrote:
>Schedule process (recommended here to work on my other post).
> Vantage 8.03.408A
>
> I am reviewing the detailed log file generated from the Global
>date selected. Reviewing these logs I am now questioning my assumption.
> I have always assumed the Global Reschedule forward schedules from the
It looks like it try's to backward schedule and if it cannot meet the
date it forward schedules. Note, I do not allow scheduling before today
or started operations.
>Reschedule?
> Can anybody confirm what the system is doing during a Global
>[Non-text portions of this message have been removed]
> Jeff
>