Internal error. Scheduling dates in JobOpMac file are not consi

We're Ver. 6.10.535

--- In vantage@yahoogroups.com, "markewhittaker" <markewhittaker@...>
wrote:
>
> Well, I don't know what version you are on, or what you mean
by "not
> consistent" but we are on 8.00.809c. When we were on 809b, we had
> scheduled dates on the JobOpMac file that did not match the
scheduled
> dates on the JobOper table. We did not actually get an error
> message, just something that I noticed.
>
> We just installed the 809c patch yesterday and did another regen
last
> night. It got rid of some other errors we were getting in the
server
> log during mrp, but now we have NO scheduled dates in the JobOper
or
> JobHead tables for MRP jobs. And there are not even any records
for
> MRP jobs in the JobOpMac table. And the schedule dates for the
firm
> jobs in the JobOpMac table still do not match the dates in the
> JobOper table.
>
> I would be interested in knowing which version you are running.
>
> --- In vantage@yahoogroups.com, "Ace_Man" <ace_man@> wrote:
> >
> > We just started getting this error during Process MRP. I was
> wondering
> > if anyone else have come across this before. Epicor is also
looking
> > into it for me. Any help is greatly appreciated.
> >
>
We just started getting this error during Process MRP. I was wondering
if anyone else have come across this before. Epicor is also looking
into it for me. Any help is greatly appreciated.
Well, I don't know what version you are on, or what you mean by "not
consistent" but we are on 8.00.809c. When we were on 809b, we had
scheduled dates on the JobOpMac file that did not match the scheduled
dates on the JobOper table. We did not actually get an error
message, just something that I noticed.

We just installed the 809c patch yesterday and did another regen last
night. It got rid of some other errors we were getting in the server
log during mrp, but now we have NO scheduled dates in the JobOper or
JobHead tables for MRP jobs. And there are not even any records for
MRP jobs in the JobOpMac table. And the schedule dates for the firm
jobs in the JobOpMac table still do not match the dates in the
JobOper table.

I would be interested in knowing which version you are running.

--- In vantage@yahoogroups.com, "Ace_Man" <ace_man@...> wrote:
>
> We just started getting this error during Process MRP. I was
wondering
> if anyone else have come across this before. Epicor is also looking
> into it for me. Any help is greatly appreciated.
>