I am running 8.03.404B. Is anyone else having difficulty with move time
being scheduled for completed operations during a reschedule? I have
discussed this with Epicor and the developers state that this is working as
designed. Consider the following scenario with 2 days move time for each
resource group and production works Mon - Thurs. I perform a reschedule
and this is what I get...
1st Op (completed) scheduled to start 5/27/08
2nd Op (completed) scheduled to start 5/29/08
3rd Op (completed) scheduled to start 6/3/08
4th Op (open and needs to start today) scheduled to start 6/5/08.
In my opinion, if I forward schedule from today, the above stated job
should start today on the 4th op. Am I crazy, should the move time between
completed operations be calculated in a reschedule? According to Epicor,
this is how it is suppose to work.
They say this is how it's always worked but I don't think we had this
problem when running 8.03.305. If you are running an earlier version than
404 could you test this for me.
Thanks,
Tonia R. Blakely
Enterprise Systems & Logistics Manager
Automatic SMP
Ph: 256-353-1931 ext. 256
Fx: 256-355-3612
being scheduled for completed operations during a reschedule? I have
discussed this with Epicor and the developers state that this is working as
designed. Consider the following scenario with 2 days move time for each
resource group and production works Mon - Thurs. I perform a reschedule
and this is what I get...
1st Op (completed) scheduled to start 5/27/08
2nd Op (completed) scheduled to start 5/29/08
3rd Op (completed) scheduled to start 6/3/08
4th Op (open and needs to start today) scheduled to start 6/5/08.
In my opinion, if I forward schedule from today, the above stated job
should start today on the 4th op. Am I crazy, should the move time between
completed operations be calculated in a reschedule? According to Epicor,
this is how it is suppose to work.
They say this is how it's always worked but I don't think we had this
problem when running 8.03.305. If you are running an earlier version than
404 could you test this for me.
Thanks,
Tonia R. Blakely
Enterprise Systems & Logistics Manager
Automatic SMP
Ph: 256-353-1931 ext. 256
Fx: 256-355-3612