Regards,
Darryn
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
brenda mohr
Sent: 10 March 2014 10:15
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Multi Resource Scheduling Board (9.05.700B)
I wrote a BPM that shows the Part Name & Customer in place of the Job
Number. The draw back is that it can no longer be used to drop and drag
jobs, which is ok for some users. For those who may need to change the
jobs, I added a checkbox that turns off the BPM and allows the MSRB to go
back to Job Number.
Brenda
9.05.702
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Darryn Ralph
Sent: Friday, March 07, 2014 10:16 AM
To: vantage@yahoogroups.com; Epicor9 Discussion List
Subject: [Vantage] Multi Resource Scheduling Board (9.05.700B)
Hi,
Looking at the multi resource scheduling board and have a couple of
questions (Help doesn't give any answers):
. Is there any way to modify the multi resource scheduling board to
only show resource group calendar time (i.e. Standard working day and no
weekends)?
. I have currently set the blocks to show Job number/Customer ID, is
there any way to add a new option (ideally would like Job Number/Customer
Name)?
Thanks,
Darryn