have you tried increasing days of supply on the part to get one suggestion? Or put a min order qty which will then make the other suggestions not be needed. You can also use multiples with the minimums to force orders to be in the discount quantities. The MfgLotMultiple field is on the Part > Plant > Planning Tab, but the MRP guide shows it also applies to purchase suggestions.

Good Luck

Greg

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of gabelebron07
Sent: Wednesday, May 15, 2013 11:54 AM
To: vantage@yahoogroups.com
Subject: [Vantage] PO Suggestions-Help



By design, the application will create multiple releases for one single part if you group multplie PO suggestions and Buy them at once.

Application won't group all the quantities suggested in one release, it will create one release per suggestion.

Scenario1.- 1 part number, 3 PO Suggestions.

Part Number: "A"
PO Sugg1: 30 pcs
PO Sugg2: 10 pcs
PO Sugg3: 40 pcs

If you check the Buy checkbox in PO Sugg1, PO Sugg2 and PO Sugg3, then generate the PO, the Application will generate a PO for part A in line 1, and 3 different releases, R1 for 30 pcs, R2 for 10 pcs and R3 for 40 pcs.

But we wanted to group all the release together, so we deleted the releases except for 1 and added to qty to that one release. Po suggestion then asked us to buy more even thou it was already on a PO

We get Discounts for ordering over a certain Qty and won't get it if we do releases to our vendors. Is there a best practice for this?


________________________________
CONFIDENTIALITY NOTICE

The information contained in this communication, including attachments, is privileged and confidential. It is intended only for the exclusive use of the addressee. If the reader of this message is not the intended recipient, or the employee or agent responsible for delivering it to the intended recipient, you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this communication in error, please notify us at 727-578-6280 and immediately delete the communication.

"This (document/presentation) may contain technical data as defined in the International Traffic In Arms Regulations (ITAR) 22 CFR 120.10. Export of this material is restricted by the Arms Export Control Act (22 U.S.C. 2751 et seq.) and may not be exported to foreign persons without prior approval form the U.S. Department of State."


[Non-text portions of this message have been removed]
By design, the application will create multiple releases for one single part if you group multplie PO suggestions and Buy them at once.

Application won't group all the quantities suggested in one release, it will create one release per suggestion.

Scenario1.- 1 part number, 3 PO Suggestions.

Part Number: "A"
PO Sugg1: 30 pcs
PO Sugg2: 10 pcs
PO Sugg3: 40 pcs

If you check the Buy checkbox in PO Sugg1, PO Sugg2 and PO Sugg3, then generate the PO, the Application will generate a PO for part A in line 1, and 3 different releases, R1 for 30 pcs, R2 for 10 pcs and R3 for 40 pcs.

But we wanted to group all the release together, so we deleted the releases except for 1 and added to qty to that one release. Po suggestion then asked us to buy more even thou it was already on a PO

We get Discounts for ordering over a certain Qty and won't get it if we do releases to our vendors. Is there a best practice for this?
By design, the application will create multiple releases for one single part if you group multplie PO suggestions and Buy them at once.

Application won't group all the quantities suggested in one release, it will create one release per suggestion.

Scenario1.- 1 part number, 3 PO Suggestions.

Part Number: "A"
PO Sugg1: 30 pcs
PO Sugg2: 10 pcs
PO Sugg3: 40 pcs

If you check the Buy checkbox in PO Sugg1, PO Sugg2 and PO Sugg3, then generate the PO, the Application will generate a PO for part A in line 1, and 3 different releases, R1 for 30 pcs, R2 for 10 pcs and R3 for 40 pcs.

But we wanted to group all the release together, so we deleted the releases except for 1 and added to qty to that one release. Po suggestion then asked us to buy more even thou it was already on a PO

We get Discounts for ordering over a certain Qty and won't get it if we do releases to our vendors. Is there a best practice for this?