Think I might be pushing it here but when adding the additional capabilities, does the system think through which machine it selected before determining which operator to select?
The example I have is a capability for machines where there are 3 machines to choose from based on availability. The additional capabilities we have added are based on machine, so if there are 3 machines in one capability, there are 3 additional capabilities with “operators” to run those machines.
What I would like the schedule to do is look at which machine was selected for the machine capability and choose the “operator” who can run that specific machine, not 3 operators who can run the 3 machines that are listed under the capability.