Why don't raw material items show up on PO suggestions

We need a good checklist for this stuff here. I made this list years ago, but it does not cover this - it was more about troubleshooting unfirm jobs.

OK, so here’s a crack at it, and others have covered a lot of this already.

Why don't I see demand to buy the material on this job

  1. Is it actually material on the job, and not a subassembly? (in your case, yes it is material - good)
  2. Does the material have a Required quantity? (not just a qty per parent)
  3. Has the material been issued complete already?
  4. Is the part set up as purchased on the main screen of Part Entry?
  5. Is the part set up as purchased for this site in Part Entry (on the Sites tab/card)?
  6. Is the part set up as Generate PO Suggestions = true
  7. Does the job have a req by date?
  8. Does the job have a due date?
  9. Does the material itself have a req by date?
  10. Is the job firm?
  11. Is the job released?
  12. Is the job scheduled?

Also, what does Time Phase look like for the raw material part? Can you find this job material in Time Phase? Does it have a date?

And I can keep editing this list with everyone’s thoughts.