Go into Job Adjustment - select the SubContract tab.

Uncheck the operation complete box.


Operations have a secondary table that has to be run to update the operation complete box, unlike materials which you can update the Issue Complete field.



I have a JobOper record that has the opComplete flag set and it is preventing a PO release associated with that subcontract operation from being changed. It appears that it boils down to opComplete being set. The field help indicates that it cannot be changed through job entry but can be changed by any receipt entry record associated with the job operation. I tried that but the checkbox for it comes up gray.

 

I tried a quick updatable dashboard but could not configure it to change the joboper.opComplete value.

 

Part of me wants to just bully it in SQL, but I know that isn’t the right answer. How do I uncomplete a job operation where the operation is a subcontract?

 

Regards,

 

Tom Christie |  Information Technology Manager  |  AGM Container Controls, Inc.  |   tchristie@...  | t: 520.881.2130 ext 2176

 

Job cost adjustment.

Sent from Yahoo Mail on Android



From: Tom J. Christie <tchristie@...>;
To: vantage@yahoogroups.com <vantage@yahoogroups.com>;
Subject: [Vantage] A weird problem
Sent: Fri, Jan 31, 2014 10:38:12 PM

Â
<div id="ygrps-yiv-330448400ygrp-text">
  
  
  <p>

I have a JobOper record that has the opComplete flag set and it is preventing a PO release associated with that subcontract operation from being changed. It appears that it boils down to opComplete being set. The field help indicates that it cannot be changed through job entry but can be changed by any receipt entry record associated with the job operation. I tried that but the checkbox for it comes up gray.

Â

I tried a quick updatable dashboard but could not configure it to change the joboper.opComplete value.

Â

Part of me wants to just bully it in SQL, but I know that isn’t the right answer. How do I uncomplete a job operation where the operation is a subcontract?

Â

Regards,

Â

Tom Christie | Information Technology Manager | AGM Container Controls, Inc. |  tchristie@... | t: 520.881.2130 ext 2176

Â

</div>
 


<div style="color:#fff;height:0;"></div></div>

What version are you on?

 

 

 

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Tom J. Christie
Sent: Friday, January 31, 2014 3:38 PM
To: vantage@yahoogroups.com
Subject: [Vantage] A weird problem

 

 

I have a JobOper record that has the opComplete flag set and it is preventing a PO release associated with that subcontract operation from being changed. It appears that it boils down to opComplete being set. The field help indicates that it cannot be changed through job entry but can be changed by any receipt entry record associated with the job operation. I tried that but the checkbox for it comes up gray.

 

I tried a quick updatable dashboard but could not configure it to change the joboper.opComplete value.

 

Part of me wants to just bully it in SQL, but I know that isn’t the right answer. How do I uncomplete a job operation where the operation is a subcontract?

 

Regards,

 

Tom Christie |  Information Technology Manager  |  AGM Container Controls, Inc.  |   tchristie@...  | t: 520.881.2130 ext 2176