Henry,
I did have 0 but changed to 730 for 2 years as suggested at one point.
I think I have everything set just as you showed in your reply now. I did notice that I didn’t have the Finite Horizon set on the resource group but I did now. A job has been entered on top of all the ones I already created and it was still scheduled as an overload.
Is there some kind of process that needs to be run after a finite horizon has been changed in the system?