Change And New PO Suggestions In 8.03.305K

No apology necessary Rob, this is all very good stuff.

It doesn't matter how many times you pilot the system before going
live, these issues only really come out when you are running it for
real. You just have to experiment so as to learn all the things the
book and the consultants don't actually tell you. That said when you
buy a car the salesman doesn't expect to have to tell you how to
drive, merely where all the knobs and dials are. :o)

We are coming from a non MRP background, and being a contract
manufacturer we make everybody else's products and not our own. That
places you in a position where you are not in control of your own
destiny, you have a very wide range of parts to manage, very low long
term visibility of demand, constant change, and your customers
inherently expect you to clean up the inadequacies of their own
poorly run systems. Now that is challenging!

Getting MRP to behave is proving interesting, however we have been
sensisible in that we have only gone live with a handful of products.
We are making lots of mistakes but this is also teaching us how to
run the system properly and everytime a new product is loaded and run
in Vantage, its better than the previous one.

The training and cultural issues are huge. We realise now that a lot
of problems with our previous system where caused directly by poor
procedural control and operators who did not keep the system properly
maintained. Vantage provides much better inventory controls than we
had previously and therefore I can now see how bad things where! :o(

Writing procedures / process flow-charts is as important as any other
aspect of running Vantage.

Thanks again for the advice Rob, its always welcome.

Nick

--- In vantage@yahoogroups.com, Robert Brown <robertb_versa@...>
wrote:
>
> Nick,
>
> Sorry for the length of the reply. I'm cursed with 'blabber
fingers' re email and tend to include so much detail the central
message can get lost.
>
> There as are some things that are best experimented with in your
non-live training/test db and somethings that are no risk at testing
in your live system.
>
> I'm of the opinion the MRP is in the no risk - test in the live
system category as you can always immediately rerun it using your old
parameters if you aren't happy with results.
>
>
> Deleting messages can be done - but it is a losing game as, unless
you fix the root cause (Example: mis-set safety/Min OH, etc.,) you
will just get the message again the next time MRP (or Generate
Purchasing Suggestions on its own) is run.
>
> Before playing with limiting the scope of MRP re 'frozen schedule'
fences, I would first get the planners/buyers involved by having them
determine & categorize WHY they are getting overwhelmed with
messages. Have them discussing the issue they uncover (daily) so you
and they can assess what commonality of the drivers of these messages
exists (and which ones are wasting your collective time the most) -
and then adjusting planning policies (safety or Min OH calc rules,
allowable days early/late, etc.,) to suit.
>
> That will allow you to mass review and pro-actively 'fix' part
planning field data to bring them in compliance with your new
systemic policies - and to get a quick positive impact from the
decisions made.
>
>
> You might take a wrong turn on some decisions - or make changes too
large in magnitude (and have to scale back to get optimum results)
but, again - nothing you do can't be 'undone'. You just have to have
your team committed to working on it and communicating with you and
each other so you can assess the effectiveness of changes (and either
increase their magnitude or reverse them) QUICKLY.
>
> Good luck!
>
> Rob Brown
>
>
>
>
>
>
>
> --- On Sun, 7/20/08, nmtaylor1969 <n.taylor@...> wrote:
> From: nmtaylor1969 <n.taylor@...>
> Subject: [Vantage] Re: Change And New PO Suggestions In 8.03.305K
> To: vantage@yahoogroups.com
> Date: Sunday, July 20, 2008, 3:26 PM
>
>
>
>
>
>
>
>
>
>
>
>
>
> Rob,
>
>
>
> I have read this through 5 times and now my head hurts...! ;o)
>
>
>
> There is some really good stuff here, some of which is probably
>
> obvious to you ( like specifying an MRP cut-off date ), but I had
not
>
> thought about this!! :o(
>
>
>
> I am going to run a few tests in our test database and I will let
you
>
> know how we get on.
>
>
>
> Do you ever just delete suggestions if they are nothing more than
>
> noise ?
>
>
>
> Many thanks,
>
>
>
> Nick
>
>
>
> --- In vantage@yahoogroups .com, Robert Brown <robertb_versa@ ...>
>
> wrote:
>
> >
>
> > Nick,
>
> >
>
> > YES:
>
> >
>
> > (A.) If you have not set up (appropriate for you & your
processes)
>
> limiting criteria on your POs such as:
>
> >
>
> > (1) Locking Qty: so MRP doesn't tell you to reduce a PO qty
due
>
> this week and then also tell you to increase a PO qty for the same
>
> part due NEXT week.
>
> >
>
> > (2) Locking Schedules: so MRP won't tell you to move an Open
PO
>
> release delivery schedule in - just to tell you to move then next
one
>
> due (same part/PO/line) OUT.
>
> >
>
> > (B.) If you have not set up (appropriate for you & your
processes)
>
> message limiting criteria on you Parts such as:
>
> >
>
> > (1) Regularly reassessed and maintained Safety, Min O/H
>
> (perhaps Days Supply place as Mark W has reported to have found
works
>
> well in his environment) , Order to Max (if a non zero Max exists)
>
> >
>
> > (2) Accurate & maintain MRP Min/Max/Multi order suggestion
>
> qty's for your Parts.
>
> >
>
> > (3) Allowable "Days Early" and "Days Late" Part tolerences
for
>
> MRP messaging. (Only POs Early more than your "Days Early" value
will
>
> appear in your exception messages & vice-versa.
>
> >
>
> > (C.) Limited MRP itself by specifying the 'frozen zone' through
>
> which MRP should not generate messages (defined as 'today' thru the
>
> Start Date value you can enter when running MRP).
>
> >
>
> > (D.) Vendor Kanbans (when you & your vendors are ready to handle
>
> certain short lead time parts this way).
>
> >
>
> > (E.) Contract POs (when you & your vendors are ready to handle
>
> inherently long lead time parts this way).
>
> >
>
> > CAREFUL experimenting with of use of these controlling elements
can
>
> turn MRP messages from being 85% noise & 15% valid, trustworthy
>
> content to up to a 50/50 split (with far fewer messages overall).
>
> >
>
> > Even with these things appropriately (for your conditions and
>
> processes) in use, you still need to see each part's message as a
>
> whole rather than stumble upon them one at a time as New, Cancel or
>
> Change messages.
>
> >
>
> > That is what Time Phase is for (as messages ARE often
>
> interdependent) .
>
> >
>
> > A good rule of thumb: Review (in Time phase) you parts with New
PO
>
> suggestions first (grouped by vendor and sub sorted by 'place order
>
> by' date) and process as appropriate (or tweak your Open PO qty or
>
> date locking & each part's MRP factors so you get won't get an
>
> inappropriate message next time) - Perhaps out only a few weeks
>
> by 'place order by' date.
>
> >
>
> > Run a net change.
>
> >
>
> > Review any change messages next (by vendor by message type and
>
> suggested change date). Move IN messages 1st, Move Out 2nd, Cancel
>
> last. (Run net change between each.)
>
> >
>
> > A few weeks of aggressively following such a process (as well
>
> experimenting with MRP options & implementing Kan-Bans or Contract
>
> POs where appropriate) and your messaging will begin to take on
some
>
> pertinence (and your Buyers won't be totally frustrated).
>
> >
>
> > Also: Don't feel compelled to do everything out of Buyers WB if
you
>
> adopt this 'message type' sequence processing. Run one less
(context
>
> linked) app and use New PO Suggestions directly and then Change
>
> Suggestions directly.
>
> >
>
> > ...MRP optimization "101" on ANY system - not just Vantage (as
MRP
>
> is a very blunt tool out of the box and needs to be sharpened to
fit
>
> your conditions, Buyer resource limitations and processes). Your
>
> Buyers must be part of 'sharpening' that tool as they know their
>
> parts/vendors - and it will give them a sense of empowerment and
>
> build a culture of teamwork.
>
> >
>
> > Go Lean & KanBan aggressively (simultaneously) as MRP 'push' on
its
>
> own drives inventory levels higher (even when optimized) whereas
>
> Lean/KanBan 'pull' does not (when done right - and what is 'right'
>
> today may not be 'right' next month/quarter if/when business
>
> conditions & part usage patterns inevitably change).
>
> >
>
> > Good luck (and make it 'fun' for your people as it is a culture
>
> change for most companies to become proactive instead of reactive).
>
> >
>
> > Rob Brown
>
> >
>
> >
>
> >
>
> >
>
> >
>
> >
>
> >
>
> > --- On Sun, 7/20/08, nmtaylor1969 <n.taylor@ .> wrote:
>
> > From: nmtaylor1969 <n.taylor@ .>
>
> > Subject: [Vantage] Change And New PO Suggestions In 8.03.305K
>
> > To: vantage@yahoogroups .com
>
> > Date: Sunday, July 20, 2008, 5:26 AM
>
> >
>
> >
>
> > Can anyone tell me if they have found the need to see both PO
>
> change
>
> > and new PO suggestions all in once place ?
>
> >
>
> > We are fairly new to running a formal MRP system and we are
>
> > generating a lot of "suggestion noise" mainly due to the MRP
>
> rules /
>
> > planning processes not being fully implemented yet. Obviously we
>
> will
>
> > rationalise this with time and a greater experience of running
the
>
> > system.
>
> >
>
> > I am finding it difficult to see the whole picture because change
>
> > suggestions are in once place, and new suggestions in another. In
>
> > some cases new suggestions represent the other half of a
>
> cancellation
>
> > change suggestion elsewhere, and the picture must be viewed in
its
>
> > entirety before an action can be taken.
>
> >
>
> > Has anybody written a dashboard to do this, or should it be an
>
> > unnecessary requirement if our system is running correctly... ?
>
> >
>
> > Thanks,
>
> >
>
> > Nick
>
> >
>
Can anyone tell me if they have found the need to see both PO change
and new PO suggestions all in once place ?

We are fairly new to running a formal MRP system and we are
generating a lot of "suggestion noise" mainly due to the MRP rules /
planning processes not being fully implemented yet. Obviously we will
rationalise this with time and a greater experience of running the
system.

I am finding it difficult to see the whole picture because change
suggestions are in once place, and new suggestions in another. In
some cases new suggestions represent the other half of a cancellation
change suggestion elsewhere, and the picture must be viewed in its
entirety before an action can be taken.

Has anybody written a dashboard to do this, or should it be an
unnecessary requirement if our system is running correctly...?

Thanks,

Nick
Nick,

YES:

(A.) If you have not set up (appropriate for you & your processes) limiting criteria on your POs such as:

(1) Locking Qty: so MRP doesn't tell you to reduce a PO qty due this week and then also tell you to increase a PO qty for the same part due NEXT week.

(2) Locking Schedules: so MRP won't tell you to move an Open PO release delivery schedule in - just to tell you to move then next one due (same part/PO/line) OUT.

(B.) If you have not set up (appropriate for you & your processes) message limiting criteria on you Parts such as:

(1) Regularly reassessed and maintained Safety, Min O/H (perhaps Days Supply place as Mark W has reported to have found works well in his environment), Order to Max (if a non zero Max exists)

(2) Accurate & maintain MRP Min/Max/Multi order suggestion qty's for your Parts.

(3) Allowable "Days Early" and "Days Late" Part tolerences for MRP messaging. (Only POs Early more than your "Days Early" value will appear in your exception messages & vice-versa.

(C.) Limited MRP itself by specifying the 'frozen zone' through which MRP should not generate messages (defined as 'today' thru the Start Date value you can enter when running MRP).

(D.) Vendor Kanbans (when you & your vendors are ready to handle certain short lead time parts this way).

(E.) Contract POs (when you & your vendors are ready to handle inherently long lead time parts this way).

CAREFUL experimenting with of use of these controlling elements can turn MRP messages from being 85% noise & 15% valid, trustworthy content to up to a 50/50 split (with far fewer messages overall).

Even with these things appropriately (for your conditions and processes) in use, you still need to see each part's message as a whole rather than stumble upon them one at a time as New, Cancel or Change messages.

That is what Time Phase is for (as messages ARE often interdependent).

A good rule of thumb: Review (in Time phase) you parts with New PO suggestions first (grouped by vendor and sub sorted by 'place order by' date) and process as appropriate (or tweak your Open PO qty or date locking & each part's MRP factors so you get won't get an inappropriate message next time) - Perhaps out only a few weeks by 'place order by' date.

Run a net change.

Review any change messages next (by vendor by message type and suggested change date). Move IN messages 1st, Move Out 2nd, Cancel last. (Run net change between each.)

A few weeks of aggressively following such a process (as well experimenting with MRP options & implementing Kan-Bans or Contract POs where appropriate) and your messaging will begin to take on some pertinence (and your Buyers won't be totally frustrated).

Also: Don't feel compelled to do everything out of Buyers WB if you adopt this 'message type' sequence processing. Run one less (context linked) app and use New PO Suggestions directly and then Change Suggestions directly.

...MRP optimization "101" on ANY system - not just Vantage (as MRP is a very blunt tool out of the box and needs to be sharpened to fit your conditions, Buyer resource limitations and processes). Your Buyers must be part of 'sharpening' that tool as they know their parts/vendors - and it will give them a sense of empowerment and build a culture of teamwork.

Go Lean & KanBan aggressively (simultaneously) as MRP 'push' on its own drives inventory levels higher (even when optimized) whereas Lean/KanBan 'pull' does not (when done right - and what is 'right' today may not be 'right' next month/quarter if/when business conditions & part usage patterns inevitably change).

Good luck (and make it 'fun' for your people as it is a culture change for most companies to become proactive instead of reactive).

Rob Brown







--- On Sun, 7/20/08, nmtaylor1969 <n.taylor@...> wrote:
From: nmtaylor1969 <n.taylor@...>
Subject: [Vantage] Change And New PO Suggestions In 8.03.305K
To: vantage@yahoogroups.com
Date: Sunday, July 20, 2008, 5:26 AM


Can anyone tell me if they have found the need to see both PO change
and new PO suggestions all in once place ?

We are fairly new to running a formal MRP system and we are
generating a lot of "suggestion noise" mainly due to the MRP rules /
planning processes not being fully implemented yet. Obviously we will
rationalise this with time and a greater experience of running the
system.

I am finding it difficult to see the whole picture because change
suggestions are in once place, and new suggestions in another. In
some cases new suggestions represent the other half of a cancellation
change suggestion elsewhere, and the picture must be viewed in its
entirety before an action can be taken.

Has anybody written a dashboard to do this, or should it be an
unnecessary requirement if our system is running correctly... ?

Thanks,

Nick
Rob,

I have read this through 5 times and now my head hurts...! ;o)

There is some really good stuff here, some of which is probably
obvious to you ( like specifying an MRP cut-off date ), but I had not
thought about this!! :o(

I am going to run a few tests in our test database and I will let you
know how we get on.

Do you ever just delete suggestions if they are nothing more than
noise ?

Many thanks,

Nick

--- In vantage@yahoogroups.com, Robert Brown <robertb_versa@...>
wrote:
>
> Nick,
>
> YES:
>
> (A.) If you have not set up (appropriate for you & your processes)
limiting criteria on your POs such as:
>
> (1) Locking Qty: so MRP doesn't tell you to reduce a PO qty due
this week and then also tell you to increase a PO qty for the same
part due NEXT week.
>
> (2) Locking Schedules: so MRP won't tell you to move an Open PO
release delivery schedule in - just to tell you to move then next one
due (same part/PO/line) OUT.
>
> (B.) If you have not set up (appropriate for you & your processes)
message limiting criteria on you Parts such as:
>
> (1) Regularly reassessed and maintained Safety, Min O/H
(perhaps Days Supply place as Mark W has reported to have found works
well in his environment), Order to Max (if a non zero Max exists)
>
> (2) Accurate & maintain MRP Min/Max/Multi order suggestion
qty's for your Parts.
>
> (3) Allowable "Days Early" and "Days Late" Part tolerences for
MRP messaging. (Only POs Early more than your "Days Early" value will
appear in your exception messages & vice-versa.
>
> (C.) Limited MRP itself by specifying the 'frozen zone' through
which MRP should not generate messages (defined as 'today' thru the
Start Date value you can enter when running MRP).
>
> (D.) Vendor Kanbans (when you & your vendors are ready to handle
certain short lead time parts this way).
>
> (E.) Contract POs (when you & your vendors are ready to handle
inherently long lead time parts this way).
>
> CAREFUL experimenting with of use of these controlling elements can
turn MRP messages from being 85% noise & 15% valid, trustworthy
content to up to a 50/50 split (with far fewer messages overall).
>
> Even with these things appropriately (for your conditions and
processes) in use, you still need to see each part's message as a
whole rather than stumble upon them one at a time as New, Cancel or
Change messages.
>
> That is what Time Phase is for (as messages ARE often
interdependent).
>
> A good rule of thumb: Review (in Time phase) you parts with New PO
suggestions first (grouped by vendor and sub sorted by 'place order
by' date) and process as appropriate (or tweak your Open PO qty or
date locking & each part's MRP factors so you get won't get an
inappropriate message next time) - Perhaps out only a few weeks
by 'place order by' date.
>
> Run a net change.
>
> Review any change messages next (by vendor by message type and
suggested change date). Move IN messages 1st, Move Out 2nd, Cancel
last. (Run net change between each.)
>
> A few weeks of aggressively following such a process (as well
experimenting with MRP options & implementing Kan-Bans or Contract
POs where appropriate) and your messaging will begin to take on some
pertinence (and your Buyers won't be totally frustrated).
>
> Also: Don't feel compelled to do everything out of Buyers WB if you
adopt this 'message type' sequence processing. Run one less (context
linked) app and use New PO Suggestions directly and then Change
Suggestions directly.
>
> ...MRP optimization "101" on ANY system - not just Vantage (as MRP
is a very blunt tool out of the box and needs to be sharpened to fit
your conditions, Buyer resource limitations and processes). Your
Buyers must be part of 'sharpening' that tool as they know their
parts/vendors - and it will give them a sense of empowerment and
build a culture of teamwork.
>
> Go Lean & KanBan aggressively (simultaneously) as MRP 'push' on its
own drives inventory levels higher (even when optimized) whereas
Lean/KanBan 'pull' does not (when done right - and what is 'right'
today may not be 'right' next month/quarter if/when business
conditions & part usage patterns inevitably change).
>
> Good luck (and make it 'fun' for your people as it is a culture
change for most companies to become proactive instead of reactive).
>
> Rob Brown
>
>
>
>
>
>
>
> --- On Sun, 7/20/08, nmtaylor1969 <n.taylor@...> wrote:
> From: nmtaylor1969 <n.taylor@...>
> Subject: [Vantage] Change And New PO Suggestions In 8.03.305K
> To: vantage@yahoogroups.com
> Date: Sunday, July 20, 2008, 5:26 AM
>
>
> Can anyone tell me if they have found the need to see both PO
change
> and new PO suggestions all in once place ?
>
> We are fairly new to running a formal MRP system and we are
> generating a lot of "suggestion noise" mainly due to the MRP
rules /
> planning processes not being fully implemented yet. Obviously we
will
> rationalise this with time and a greater experience of running the
> system.
>
> I am finding it difficult to see the whole picture because change
> suggestions are in once place, and new suggestions in another. In
> some cases new suggestions represent the other half of a
cancellation
> change suggestion elsewhere, and the picture must be viewed in its
> entirety before an action can be taken.
>
> Has anybody written a dashboard to do this, or should it be an
> unnecessary requirement if our system is running correctly... ?
>
> Thanks,
>
> Nick
>
Nick,

Sorry for the length of the reply. I'm cursed with 'blabber fingers' re email and tend to include so much detail the central message can get lost.

There as are some things that are best experimented with in your non-live training/test db and somethings that are no risk at testing in your live system.

I'm of the opinion the MRP is in the no risk - test in the live system category as you can always immediately rerun it using your old parameters if you aren't happy with results.


Deleting messages can be done - but it is a losing game as, unless you fix the root cause (Example: mis-set safety/Min OH, etc.,) you will just get the message again the next time MRP (or Generate Purchasing Suggestions on its own) is run.

Before playing with limiting the scope of MRP re 'frozen schedule' fences, I would first get the planners/buyers involved by having them determine & categorize WHY they are getting overwhelmed with messages. Have them discussing the issue they uncover (daily) so you and they can assess what commonality of the drivers of these messages exists (and which ones are wasting your collective time the most) - and then adjusting planning policies (safety or Min OH calc rules, allowable days early/late, etc.,) to suit.

That will allow you to mass review and pro-actively 'fix' part planning field data to bring them in compliance with your new systemic policies - and to get a quick positive impact from the decisions made.


You might take a wrong turn on some decisions - or make changes too large in magnitude (and have to scale back to get optimum results) but, again - nothing you do can't be 'undone'. You just have to have your team committed to working on it and communicating with you and each other so you can assess the effectiveness of changes (and either increase their magnitude or reverse them) QUICKLY.

Good luck!

Rob Brown







--- On Sun, 7/20/08, nmtaylor1969 <n.taylor@...> wrote:
From: nmtaylor1969 <n.taylor@...>
Subject: [Vantage] Re: Change And New PO Suggestions In 8.03.305K
To: vantage@yahoogroups.com
Date: Sunday, July 20, 2008, 3:26 PM













Rob,



I have read this through 5 times and now my head hurts...! ;o)



There is some really good stuff here, some of which is probably

obvious to you ( like specifying an MRP cut-off date ), but I had not

thought about this!! :o(



I am going to run a few tests in our test database and I will let you

know how we get on.



Do you ever just delete suggestions if they are nothing more than

noise ?



Many thanks,



Nick



--- In vantage@yahoogroups .com, Robert Brown <robertb_versa@ ...>

wrote:

>

> Nick,

>

> YES:

>

> (A.) If you have not set up (appropriate for you & your processes)

limiting criteria on your POs such as:

>

> (1) Locking Qty: so MRP doesn't tell you to reduce a PO qty due

this week and then also tell you to increase a PO qty for the same

part due NEXT week.

>

> (2) Locking Schedules: so MRP won't tell you to move an Open PO

release delivery schedule in - just to tell you to move then next one

due (same part/PO/line) OUT.

>

> (B.) If you have not set up (appropriate for you & your processes)

message limiting criteria on you Parts such as:

>

> (1) Regularly reassessed and maintained Safety, Min O/H

(perhaps Days Supply place as Mark W has reported to have found works

well in his environment) , Order to Max (if a non zero Max exists)

>

> (2) Accurate & maintain MRP Min/Max/Multi order suggestion

qty's for your Parts.

>

> (3) Allowable "Days Early" and "Days Late" Part tolerences for

MRP messaging. (Only POs Early more than your "Days Early" value will

appear in your exception messages & vice-versa.

>

> (C.) Limited MRP itself by specifying the 'frozen zone' through

which MRP should not generate messages (defined as 'today' thru the

Start Date value you can enter when running MRP).

>

> (D.) Vendor Kanbans (when you & your vendors are ready to handle

certain short lead time parts this way).

>

> (E.) Contract POs (when you & your vendors are ready to handle

inherently long lead time parts this way).

>

> CAREFUL experimenting with of use of these controlling elements can

turn MRP messages from being 85% noise & 15% valid, trustworthy

content to up to a 50/50 split (with far fewer messages overall).

>

> Even with these things appropriately (for your conditions and

processes) in use, you still need to see each part's message as a

whole rather than stumble upon them one at a time as New, Cancel or

Change messages.

>

> That is what Time Phase is for (as messages ARE often

interdependent) .

>

> A good rule of thumb: Review (in Time phase) you parts with New PO

suggestions first (grouped by vendor and sub sorted by 'place order

by' date) and process as appropriate (or tweak your Open PO qty or

date locking & each part's MRP factors so you get won't get an

inappropriate message next time) - Perhaps out only a few weeks

by 'place order by' date.

>

> Run a net change.

>

> Review any change messages next (by vendor by message type and

suggested change date). Move IN messages 1st, Move Out 2nd, Cancel

last. (Run net change between each.)

>

> A few weeks of aggressively following such a process (as well

experimenting with MRP options & implementing Kan-Bans or Contract

POs where appropriate) and your messaging will begin to take on some

pertinence (and your Buyers won't be totally frustrated).

>

> Also: Don't feel compelled to do everything out of Buyers WB if you

adopt this 'message type' sequence processing. Run one less (context

linked) app and use New PO Suggestions directly and then Change

Suggestions directly.

>

> ...MRP optimization "101" on ANY system - not just Vantage (as MRP

is a very blunt tool out of the box and needs to be sharpened to fit

your conditions, Buyer resource limitations and processes). Your

Buyers must be part of 'sharpening' that tool as they know their

parts/vendors - and it will give them a sense of empowerment and

build a culture of teamwork.

>

> Go Lean & KanBan aggressively (simultaneously) as MRP 'push' on its

own drives inventory levels higher (even when optimized) whereas

Lean/KanBan 'pull' does not (when done right - and what is 'right'

today may not be 'right' next month/quarter if/when business

conditions & part usage patterns inevitably change).

>

> Good luck (and make it 'fun' for your people as it is a culture

change for most companies to become proactive instead of reactive).

>

> Rob Brown

>

>

>

>

>

>

>

> --- On Sun, 7/20/08, nmtaylor1969 <n.taylor@.. .> wrote:

> From: nmtaylor1969 <n.taylor@.. .>

> Subject: [Vantage] Change And New PO Suggestions In 8.03.305K

> To: vantage@yahoogroups .com

> Date: Sunday, July 20, 2008, 5:26 AM

>

>

> Can anyone tell me if they have found the need to see both PO

change

> and new PO suggestions all in once place ?

>

> We are fairly new to running a formal MRP system and we are

> generating a lot of "suggestion noise" mainly due to the MRP

rules /

> planning processes not being fully implemented yet. Obviously we

will

> rationalise this with time and a greater experience of running the

> system.

>

> I am finding it difficult to see the whole picture because change

> suggestions are in once place, and new suggestions in another. In

> some cases new suggestions represent the other half of a

cancellation

> change suggestion elsewhere, and the picture must be viewed in its

> entirety before an action can be taken.

>

> Has anybody written a dashboard to do this, or should it be an

> unnecessary requirement if our system is running correctly... ?

>

> Thanks,

>

> Nick

>