Changing shipping date

You have to unrelease/unengineer the jobs and reschedule them individually.
However, these changes should generate a manufacturing suggestion, and
selecting one of the suggestions will put you in the "links" screen. From
here you can (fairly)quickly update and reschedule all 5 jobs.

-----Original Message-----
From: venky@... [mailto:venky@...]
Sent: Friday, August 18, 2000 7:25 AM
To: vantage@egroups.com
Subject: [Vantage] Changing shipping date


I have a sales order already linked to 5 jobs. These 5 jobs have been
scheduled. The customer now has changed the shipping date on the
sales order, so I updated the new shipping date and need date on the
sales order. However, this did not change the shipping date on the 5
jobs. Does that mean that I have to unrelease each job and update the
new shipping date and reschedule all 5 jobs. Does any one know any
easier way of doing this.

Thank you
I have a sales order already linked to 5 jobs. These 5 jobs have been
scheduled. The customer now has changed the shipping date on the
sales order, so I updated the new shipping date and need date on the
sales order. However, this did not change the shipping date on the 5
jobs. Does that mean that I have to unrelease each job and update the
new shipping date and reschedule all 5 jobs. Does any one know any
easier way of doing this.

Thank you