Does anyone know for sure whether the Days Out field on subcontract operations is in working days or calendar days?
Days Out in Subcontract Op (Engineering Workbench > Method of Mfg) in Working Days or Calendar Days?
That will be calendar days based on the calendar on the Supplier record. If there is no calendar on the Supplier record then it will use the Resource Group, then Site default, then Company default.