If a job was attached to a project and the costs associated with the job posted to the project, will removing the project ID from the job, remove the costs from the project?

Yes, it should remove. But I haven’t tried myself. :grinning:

Agree with @Arul. But if you’re using an advanced billing method like Cost Plus and you’ve already invoiced then you may have issues. Otherwise the next run of Build Project Analysis should remove the costs.

I’m not talking about a billable project. It’s an internal project.

Thanks,

Tim Carpenter