Trying to figure out the Capable to Promise logic. Does it consider unfirm jobs from MRP as tying up the materials or does it ignore them since they aren’t firm?
Thanks
Trying to figure out the Capable to Promise logic. Does it consider unfirm jobs from MRP as tying up the materials or does it ignore them since they aren’t firm?
Thanks
Good luck… the Capable to Promise logic can be a little convoluted. The Advanced Scheduling Education Course Guide has a pretty good discussion of how it works.
I would say, however, that it WOULD consider unfirm jobs as tying up supply, as that is how Epicor works for everything else as well. CTP is a “what-if” job suggestion generator, so it’s going to follow all the regular rules.