ECOOpr.DaysOut not updating

The days out for a subcontract operation is not updating. Check a part out in engineering workbench - change days out from 0.00 to 2 - click save - it changes back to 0.00.

I had used DMT to upload all the days out into the BOO but somehow they have been set back to 0. So system is not allowing any scheduling days for the subcontract work to be done making all jobs complete late.

Any idea why this keeps reverting back to 0?

Have you already tried adding a new revision from scratch and then testing changes to a subcontract “days out”?

and are you sure there are no BPMs?
either Erp.Proxy.BO.EngWorkBenchImpl.Update or ECOOper table?

Definitely no BPMs

This has happened to all of our subcontract operations…they all show 0 days out.

I’m wondering if the lead time in Supplier Price List for these subcontract parts overrides the days out in the BOO

I did some playing around and testing…

ECO Opr. - Days Out - will default to whatever you have as lead time in Supplier Price List. You can not over ride it - as soon as you hit save - it reverts back to whatever it shows as lead time in supplier price list.

Interesting… I wasn’t able to reproduce this.

I wonder if DMT might have missed/done something.
Or if there are any version specific bugs.
Maybe worth a call to Epicor?
Or test build a new method & new vendor prices list from scratch?