The days out for a subcontract operation is not updating. Check a part out in engineering workbench - change days out from 0.00 to 2 - click save - it changes back to 0.00.
I had used DMT to upload all the days out into the BOO but somehow they have been set back to 0. So system is not allowing any scheduling days for the subcontract work to be done making all jobs complete late.
ECO Opr. - Days Out - will default to whatever you have as lead time in Supplier Price List. You can not over ride it - as soon as you hit save - it reverts back to whatever it shows as lead time in supplier price list.
I wonder if DMT might have missed/done something.
Or if there are any version specific bugs.
Maybe worth a call to Epicor?
Or test build a new method & new vendor prices list from scratch?