Generate Purchasing Suggestions

If your Buyers are going verbal/manual purchase requests not showing in their WB, you need to run Generate Purch Suggestions as frequently as needed to make this situation go away.

I can't imagine too many environments where that wouldn't be daily.

Rob Brown

--- On Tue, 5/20/08, Darren Giordano <scubadoobydootoo@...> wrote:

From: Darren Giordano <scubadoobydootoo@...>
Subject: [Vantage] Generate Purchasing Suggestions
To: "Vantage" <vantage@yahoogroups.com>
Date: Tuesday, May 20, 2008, 11:17 AM






I was wondering how often everyone else is running Purchasing Suggestions?
We run a Regen MRP on Sunday and a Regen Purchasing Suggestions after the MRP completes, and we do not run anything more during the week.Â
Purchasing is getting a lot of requests for parts that need to be ordered but are not showing up in PO Suggestions.
So I am wondering if we need to run a Net Change during the week?
Â
Thank you,
Darren

[Non-text portions of this message have been removed]
I was wondering how often everyone else is running Purchasing Suggestions?
We run a Regen MRP on Sunday and a Regen Purchasing Suggestions after the MRP completes, and we do not run anything more during the week.Â
Purchasing is getting a lot of requests for parts that need to be ordered but are not showing up in PO Suggestions.
So I am wondering if we need to run a Net Change during the week?
Â
Thank you,
Darren




[Non-text portions of this message have been removed]
We schedule a complete regen every night at 3:00 am. We are an
electronics manufacturer with lots of parts to order.

-Peter

--- In vantage@yahoogroups.com, Darren Giordano
<scubadoobydootoo@...> wrote:
>
> I was wondering how often everyone else is running Purchasing
Suggestions?
> We run a Regen MRP on Sunday and a Regen Purchasing Suggestions
after the MRP completes, and we do not run anything more during the
week.Â
> Purchasing is getting a lot of requests for parts that need to be
ordered but are not showing up in PO Suggestions.
> So I am wondering if we need to run a Net Change during the week?
> Â
> Thank you,
> Darren
>
>
>
>
> [Non-text portions of this message have been removed]
>
We run it every morning also.

-Liz

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]On Behalf Of pvolkert365
Sent: Tuesday, May 20, 2008 10:04 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Generate Purchasing Suggestions



We schedule a complete regen every night at 3:00 am. We are an
electronics manufacturer with lots of parts to order.

-Peter

--- In vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com, Darren Giordano
<scubadoobydootoo@...> wrote:
>
> I was wondering how often everyone else is running Purchasing
Suggestions?
> We run a Regen MRP on Sunday and a Regen Purchasing Suggestions
after the MRP completes, and we do not run anything more during the
week.
> Purchasing is getting a lot of requests for parts that need to be
ordered but are not showing up in PO Suggestions.
> So I am wondering if we need to run a Net Change during the week?
>
> Thank you,
> Darren
>
>
>
>
> [Non-text portions of this message have been removed]
>







[Non-text portions of this message have been removed]
I question why you are running MRP and then running PO Suggestions. If
your Purchase parts have the MRP box checked then they are included in
the MRP run.



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Darren Giordano
Sent: Tuesday, May 20, 2008 10:18 AM
To: Vantage
Subject: [Vantage] Generate Purchasing Suggestions



I was wondering how often everyone else is running Purchasing
Suggestions?
We run a Regen MRP on Sunday and a Regen Purchasing Suggestions after
the MRP completes, and we do not run anything more during the week.
Purchasing is getting a lot of requests for parts that need to be
ordered but are not showing up in PO Suggestions.
So I am wondering if we need to run a Net Change during the week?

Thank you,
Darren

[Non-text portions of this message have been removed]



Charles Carden
Manager, MIS
Manitex, Inc.
Phone: 512-942-3086
Fax: 512-942-3089


DISCLAIMER:
This e-mail, including attachments, may include confidential and/or
proprietary information, and may be used only by the person or entity to
which it is addressed. If the reader of this e-mail is not the intended
recipient or his or her authorized agent, the reader is hereby notified
that any dissemination, distribution or copying of this e-mail is
prohibited. If you have received this e-mail in error, please notify the
sender by replying to this message and delete this e-mail immediately.



[Non-text portions of this message have been removed]
I wondered, and asked, that myself.... but pretty much it is the way the consultant installed it and the way he thinks it should be run.Â
One of the things that will get changed once the Server is relocated to my location.


----- Original Message ----
From: Charles Carden <ccarden@...>
To: vantage@yahoogroups.com
Sent: Tuesday, May 20, 2008 3:25:51 PM
Subject: RE: [Vantage] Generate Purchasing Suggestions


I question why you are running MRP and then running PO Suggestions. If
your Purchase parts have the MRP box checked then they are included in
the MRP run.

From: vantage@yahoogroups .com [mailto:vantage@yahoogroups .com] On Behalf
Of Darren Giordano
Sent: Tuesday, May 20, 2008 10:18 AM
To: Vantage
Subject: [Vantage] Generate Purchasing Suggestions

I was wondering how often everyone else is running Purchasing
Suggestions?
We run a Regen MRP on Sunday and a Regen Purchasing Suggestions after
the MRP completes, and we do not run anything more during the week.
Purchasing is getting a lot of requests for parts that need to be
ordered but are not showing up in PO Suggestions.
So I am wondering if we need to run a Net Change during the week?

Thank you,
Darren

[Non-text portions of this message have been removed]

Charles Carden
Manager, MIS
Manitex, Inc.
Phone: 512-942-3086
Fax: 512-942-3089

DISCLAIMER:
This e-mail, including attachments, may include confidential and/or
proprietary information, and may be used only by the person or entity to
which it is addressed. If the reader of this e-mail is not the intended
recipient or his or her authorized agent, the reader is hereby notified
that any dissemination, distribution or copying of this e-mail is
prohibited. If you have received this e-mail in error, please notify the
sender by replying to this message and delete this e-mail immediately.

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]
Thank you for the information!



----- Original Message ----
From: Elizabeth Hahn <ehahn@...>
To: vantage@yahoogroups.com
Sent: Tuesday, May 20, 2008 2:39:12 PM
Subject: RE: [Vantage] Re: Generate Purchasing Suggestions


We run it every morning also.

-Liz

-----Original Message-----
From: vantage@yahoogroups .com [mailto:vantage@yahoogroups .com]On Behalf Of pvolkert365
Sent: Tuesday, May 20, 2008 10:04 AM
To: vantage@yahoogroups .com
Subject: [Vantage] Re: Generate Purchasing Suggestions

We schedule a complete regen every night at 3:00 am. We are an
electronics manufacturer with lots of parts to order.

-Peter

--- In vantage@yahoogroups <mailto:vantage% 40yahoogroups. com> .com, Darren Giordano
<scubadoobydootoo@ ...> wrote:
>
> I was wondering how often everyone else is running Purchasing
Suggestions?
> We run a Regen MRP on Sunday and a Regen Purchasing Suggestions
after the MRP completes, and we do not run anything more during the
week.
> Purchasing is getting a lot of requests for parts that need to be
ordered but are not showing up in PO Suggestions.
> So I am wondering if we need to run a Net Change during the week?
>