The Maintenance Plan Processor is creating PMs without the job being Released / Engineered. How do you set up the Maintenance Plans to have these two boxes checked when they are created?
Is the only way via data directive? We have one set up and enabled.
The Maintenance Plan Processor is essentially an MRP for Maintenance… so it does the same thing the OTHER MRP does in creating Maintenance Job Suggestions.
So yes, in order to have them automagically Engineered and Released, you’d need a BPM.
1 Like
I have not tested this, but you could see if using a Method Directive on JobEntry.Update works. There is another method GetNewMaintJobUIDefaults, you could also try that).