DaveOlender
(Dave Olender)
#1
I thought there was a way to set the job completed qty using Job Adjustment - however the “completed Qty” is grayed out for me.
Is there some other place I can set the Job Completed Qty?
I don’t want to do a Job Reciept to Inventory because that will throw off my Inventory numbers.
Thanks,
DaveO
Banderson
(Brandon Anderson)
#2
Completed quantity on a job is controlled by the last operation on the job. Job receipt to inventory won’t change the quantity completed on the job.
kjarman84
(Ken Jarman)
#3
If you do a Job adjustment on the final operation, that should update the completed qty on the job.
1 Like
DaveOlender
(Dave Olender)
#4
Thank you, I see that now.
I tried that before - but the screen did not update - so I thought it was not working.
Thank you both Brandon and Ken.
DaveO