I was hoping to avoid running multiple jobs
Are you hooking the two jobs together? And when you say running concurrent is there a way to do this automatically? If I remember right there was a way for the parts to be automatically issue to the parent job because we don’t want to put them to stock and issue them. This is a continuous cell where all this is happening.
Right now we have the two parts setup as NS and listed on the parent Method as Pull and view as an assembly and we have a custom Time and expense screen that has code to allow scrapping at the operation on the method for each part
The current structure does not play well with finite scheduling which we need to be able to run as right now the scheduler has to manipulate everything manually and they are overloaded and missing customer demand