MRP Job QTY changes

Ok, an easy one but I’ve not tackled before if MRP says increase job QTY which menu(s) do you use to review/process?

Thanks (asking for a friend ;P)

That would be the Planner Workbench. It will show Increase/Decrease/Expedite/Postpone just like the Change PO Suggestions program does for purchase orders.

It will ALSO show you which parts need jobs that for some reason MRP couldn’t create.

Thanks Ernie. Like the last comment as well, wasn’t aware.

Do you need to run the Planning Workbench Process before launching the Workbench?

No, what you’re referring to is the Production Planning Process, which is a different dashboard.

And please tell “your friend” we all say hi!