"No Resources are available to schedule" error in Vantage 8

Marco, THAT DID IT!!!  Thank you so much!

 

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Marco Vissuet
Sent: Wednesday, March 12, 2014 11:35 AM
To: vantage@yahoogroups.com
Subject: [Vantage] RE: "No Resources are available to schedule" error in Vantage 8

 

 

On the operation that you cannot schedule is the JobOper.PrimaryProdOpDtlDesc field correct?

 

 

Marco Vissuet

Systems Engineering

Pacific Contours Corporation

Office (619) 670-3900

Cell (619) 507-2311

Fax (619) 670-1643

marcov@...

http://www.pacificcontours.com/

 

"The information contained herein may be subject to the International Traffic in Arms Regulations (ITAR) Warning: - This document contains data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) as amended, or the Export Administration Act (Title 50, U.S.C., App 2401 et seq.) as amended. Violations of these export laws are subject to severe criminal and civil penalties.  Disseminate in accordance with provisions of DoD Directive 5230.25.

 

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Mike Abell
Sent: Wednesday, March 12, 2014 8:54 AM
To: vantage@yahoogroups.com
Subject: [Vantage] "No Resources are available to schedule" error in Vantage 8

 

 

We are trying to get a job to schedule and we are getting a “No resources are available to schedule operation xxx”.  The resource groups needed are active and everything looks normal as we use this resource group all the time.  We have never seen this error before.  Any ideas on what might be causing this??

 

Mike Abell

Information Technology Manager
Flexial - BOA Group - Cookeville, Tennessee
Office:   931.432.8408
Mobile:  615.418.3055
 
email:  MAbell@...

 

 

We are trying to get a job to schedule and we are getting a “No resources are available to schedule operation xxx”.  The resource groups needed are active and everything looks normal as we use this resource group all the time.  We have never seen this error before.  Any ideas on what might be causing this??

 

Mike Abell

Information Technology Manager
Flexial - BOA Group - Cookeville, Tennessee
Office:   931.432.8408
Mobile:  615.418.3055
 
email:  MAbell@...

 

 

On the operation that you cannot schedule is the JobOper.PrimaryProdOpDtlDesc field correct?

 

 

Marco Vissuet

Systems Engineering

Pacific Contours Corporation

Office (619) 670-3900

Cell (619) 507-2311

Fax (619) 670-1643

marcov@...

http://www.pacificcontours.com/

 

"The information contained herein may be subject to the International Traffic in Arms Regulations (ITAR) Warning: - This document contains data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) as amended, or the Export Administration Act (Title 50, U.S.C., App 2401 et seq.) as amended. Violations of these export laws are subject to severe criminal and civil penalties.  Disseminate in accordance with provisions of DoD Directive 5230.25.

 

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Mike Abell
Sent: Wednesday, March 12, 2014 8:54 AM
To: vantage@yahoogroups.com
Subject: [Vantage] "No Resources are available to schedule" error in Vantage 8

 

 

We are trying to get a job to schedule and we are getting a “No resources are available to schedule operation xxx”.  The resource groups needed are active and everything looks normal as we use this resource group all the time.  We have never seen this error before.  Any ideas on what might be causing this??

 

Mike Abell

Information Technology Manager
Flexial - BOA Group - Cookeville, Tennessee
Office:   931.432.8408
Mobile:  615.418.3055
 
email:  MAbell@...