On the operation that you cannot schedule is the JobOper.PrimaryProdOpDtlDesc field correct?
Marco Vissuet
Systems Engineering
Pacific Contours Corporation
Office (619) 670-3900
Cell (619) 507-2311
Fax (619) 670-1643
http://www.pacificcontours.com/
"The information contained herein may be subject to the International Traffic in Arms Regulations (ITAR) Warning: - This document contains data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) as amended, or the Export Administration Act (Title 50, U.S.C., App 2401 et seq.) as amended. Violations of these export laws are subject to severe criminal and civil penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Mike Abell
Sent: Wednesday, March 12, 2014 8:54 AM
To: vantage@yahoogroups.com
Subject: [Vantage] "No Resources are available to schedule" error in Vantage 8
We are trying to get a job to schedule and we are getting a “No resources are available to schedule operation xxx”. The resource groups needed are active and everything looks normal as we use this resource group all the time. We have never seen this error before. Any ideas on what might be causing this??