Overscheduled Resources

I am looking for the resource list that is associated with the capability. Capabilities allow you to schedule ops on resources regardless of R/G construction when overloads are detected.

If this isn’t what you are looking for I’m not sure what you are asking.

In order for a capability to work properly, you have to have two resources (at least). The first is one that would normally be scheduled in the event you did not have the capability created. The second is the resource that you want to schedule in the event the first is overloaded.

The highest numbered resource will be the first one scheduled (you can number the resources yourself). This is how one looks that works here.

image

So if I have a capability that only one machine will do, scheduling won’t work? We have numerous machines that do things that other machines won’t. Does this mean that scheduling is not going to work for us? It seems almost unfathomable that there are no other companies that don’t have duplicates of every machine they have on the floor.

A capability allows you to schedule an item without the limitations of using resource groups. You can have the system select from a list of resources and look for open time to hold the schedule.

Part of that consideration is “do we have time on the originally chosen resource”? The software is going to put the labor somewhere, you just determine the sequence of equipment that the item can run.

If you have two similar machines, I would build a resource group and specify both pieces of equipment as resources inside that group.

If the capability only exists on one machine, you don’t want to specify a capability to do that. Just specify the resource group, and the exact resource that the item runs on.

1 Like

I can follow what you are saying and am going to try changing those capabilities that point to a single machine and see if that helps. Will just have to remember when we add new machines to change all the current ops. I’m really disappointed in where I was hoping to go with employees and capabilities as having to do things this way makes the capability system nearly useless with employees as turnover can often cause temporary cases of having capabilities held by a single employee temporarily which will make the scheduling system not work properly.

The oddest part about this is the fact that it is only doing this on day one of the schedules. For example, with this resource:

Day one is the only place where there are more than one job scheduled on the resource. Past job 003084-1-1 there are no more overlapping jobs even when I go out to another month. Every job from this point on is scheduled one at a time with no overlaps.

I think you may have missed my point about these being released jobs. The released jobs are not scheduled through MRP. They are scheduled when you release them, or if you convert unfirm jobs to live jobs, they are already scheduled. The point is, the method you are using to schedule your released jobs might be the driver in your overloaded resources, and the construction of the capabilities may be a contributing factor in that.

Maybe I’m confused. My understanding is that MRP creates unfirm jobs and schedules those.

When you release a job, it is scheduled.

I thought that when you ran calculate global scheduling, it determined the importance of a job based on when it is due and the priority assigned to it. You can then adjust global scheduling to make any changes to this order that you like.

I then was under the belief that if I ran global scheduling, it rescheduled released and firm jobs based on the order that had been set. Is this not true? If not, what is the point of the global scheduling? If that’s not what it does, then I’m even more confused as to what the point of locking jobs and ignoring locks, etc is.

In order to have an up to date schedule, do I need to load each individual job and reschedule it from there? I’m confused as to what the proper steps to do this are.

Your conclusions about unfirm jobs are correct. But, you indicated that when those were created and scheduled through MRP, they were scheduling finitely.

I’m trying to get you to separate the scheduling that is done through MRP versus the scheduling that is done via a global, to determine exactly what is overloading your resources. It appears that MRP scheduling is not, if your jobs are scheduled finitely.

The unfirmed jobs created by MRP are scheduling finitely.

If that is the case, then your overloaded resources are due to released jobs (which do not get touched when you run MRP) or through global scheduling. I suspect the capability as structured has a role in that, even though it may be functioning through the scheduler run in MRP. Since you’ve only specified one resource on the capability, it “should” operate as if it was a resource group with one resource in it. It might not be doing that, though.

I appreciate your help and input. I was thinking that it “should” work that way as well, but doesn’t appear to. I’m going to try changing the operations to point at the resource individually rather than using the capabilities and if it works, I will update here but that would seem to be a major fail on the part of the capability system if it won’t operate without selecting the specific resource.

I do think the capability will work as you expect, but it’s not set up properly.

What’s wrong with the setup? I must have missed something. Unless we’re still talking about there only being one resource with this capability. If that’s it, then it’s not working as I expect because I would expect it to work as if that was the resource specifically selected. If it’s something else, what do I need to change?

What would happen if you first run “Global Scheduling” (to scheduled firm jobs) and then you run the MRP ?

(Edit) Or vice-versa ? Take a look at this post : Global Scheduling vs MRP who goes first

I can try it but it should make no difference as the unfirm jobs are not part of the issue. Every job that is overscheduled is a released job. Our unfirm jobs begin with U, those firmed begin with F, and those created not by MRP begin with a 0. It’s only jobs that begin with a 0 on those resource but at this point, I’ll give it a try.

I had just run Global Scheduling so I went ahead and ran MRP and have the same results as running MRP then Global Scheduling. The sales order jobs are still the ones overscheduling.

I tried selecting resource group and resource on the operation rather than using the capability and Global Scheduling simply hangs up and doesn’t complete. If I take the resource off the operations, scheduling runs and completes. It still overschedules the resources though. For this example (M290), it once again overschedules on the first day of the schedule and then is fine from there on out. I know @Gil_V had mentioned that I possibly have the capability set up incorrectly, but I’m not seeing what I have wrong. I have posted screenshots of all the places I know that involves scheduling, resources, and capabilities so if anyone else sees what I have wrong, I would be very appreciative and if there’s anything else that may affect it that I haven’t shared, would love that input as well.

What does your scheduling log indicate?

Sorry it took me so long to respond. I realized looking at my log that the one I ran this morning I had forgot to set it to log everything so I reran scheduling with everything being logged. I ran it with a single processor and am including those logs here:

                Wednesday, September 29, 2021 13:18:09

13:18:10 Sched process begin.
13:18:10 Site List                              -> MfgSys
13:18:10 Multi Job setting activated
13:18:10 ------------------------------------------------------------
13:18:10 Process Control
13:18:10   Name -> ProcessorMain; Code -> Erp.Internal.MR.MrpExp.dll
13:18:10     Process Stop Queues -> SchedJob~SaveLoad
13:18:10     Controller -> True; Range Start -> 0; Range End -> 0
13:18:10 Version 1.00.01
13:18:10   Name -> ProcessorSched; Code -> Erp.Internal.MR.MrpExpSched.dll
13:18:10     Process Stop Queues -> 
13:18:10     Controller -> False; Range Start -> 1; Range End -> 100
13:18:10 Version 1.00.01
13:18:10 ------------------------------------------------------------
13:18:10 Process Queue
13:18:10   Name -> BuildSchedList; Queue In -> ; Queue Out -> SchedJobF; Controller -> True
13:18:10     Alt Queue Out 1 -> SchedJobI; Alt Queue Out 2 -> ; Alt Queue Out 3 -> 
13:18:10     Group -> Job; Check Group -> Job; Repeat -> False; Regen Only -> False; Finite -> False
13:18:10   Name -> ScheduleJobF; Queue In -> SchedJobF; Queue Out -> SaveLoad; Controller -> False
13:18:10     Alt Queue Out 1 -> ; Alt Queue Out 2 -> ; Alt Queue Out 3 -> 
13:18:10     Group -> Job; Check Group -> ; Repeat -> False; Regen Only -> False; Finite -> True
13:18:10   Name -> ScheduleJobI; Queue In -> SchedJobI; Queue Out -> SaveLoad; Controller -> False
13:18:10     Alt Queue Out 1 -> ; Alt Queue Out 2 -> ; Alt Queue Out 3 -> 
13:18:10     Group -> Job; Check Group -> ; Repeat -> False; Regen Only -> False; Finite -> False
13:18:10   Name -> ProcessLoad; Queue In -> ; Queue Out -> ; Controller -> True
13:18:10     Alt Queue Out 1 -> ; Alt Queue Out 2 -> ; Alt Queue Out 3 -> 
13:18:10     Group -> Load; Check Group -> Load; Repeat -> False; Regen Only -> False; Finite -> False
13:18:10   Name -> SaveLoad; Queue In -> SaveLoad; Queue Out -> Load; Controller -> False
13:18:10     Alt Queue Out 1 -> ; Alt Queue Out 2 -> ; Alt Queue Out 3 -> 
13:18:10     Group -> Load; Check Group -> ; Repeat -> False; Regen Only -> False; Finite -> False
13:18:10 ------------------------------------------------------------
13:18:10 Starting sub-processes
13:18:10 Building Job List
13:18:35 Processing Jobs...
15:21:44 Processing Schedule Load
15:25:44 Sched process finished.

and the more in depth longer one:

                Wednesday, September 29, 2021 01:18:10
01:18:10 MRP finite scheduling process begin.
01:18:10 ------------------------------------------------------------
01:18:10 Cut Off Date                      -> 
01:18:10 Schedule Start Date               -> 9/29/2021 12:00:00 AM
01:18:10 Run Finite Scheduling             -> True
01:18:10 Ignore Constrained Materials      -> False
01:18:10 Allow Historical Dates            -> False
01:18:10 Use Production Preparation Buffer -> True
01:18:10 ------------------------------------------------------------
01:18:10 Process Control Queue
01:18:10   Group -> Job; Queue -> SchedJobF; Type -> Job; Finite -> True
01:18:10   Group -> Job; Queue -> SchedJobI; Type -> Job; Finite -> False
01:18:10     Check List -> SchedJobF~SchedJobI; Last Group -> False
01:18:10   Group -> Load; Queue -> SaveLoad; Type -> Job; Finite -> False
01:18:10     Check List -> SaveLoad; Last Group -> True
01:18:10 ------------------------------------------------------------
01:18:34 Starting Part Level: 0-0.  Wait Time: 00h:00m:00s:000ms, Jobs: 0
01:18:34 Scheduling new unfirm job:003020-1-1

01:18:40 The job is currently scheduled to finish 9/29/2021.  It will not meet its required date of 7/9/2021.
01:18:40 Done Scheduling job:003020-1-1 sending job to queue SaveLoad
01:18:40 Scheduling new unfirm job:003134-1-1
01:19:06 Done Scheduling job:003134-1-1 sending job to queue SaveLoad
01:19:06 Scheduling new unfirm job:003214-1-1

01:19:23 No resources are available to schedule operation 20 of assembly 1
01:19:24 Scheduling new unfirm job:M056166
01:19:27 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/17/2021 as  the Company doesn’t allow scheduling in the past.
01:19:27 Done Scheduling job:M056166 sending job to queue SaveLoad
01:19:27 Scheduling new unfirm job:003185-1-1
01:19:31 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/18/2021 as  the Company doesn’t allow scheduling in the past.
01:19:31 Done Scheduling job:003185-1-1 sending job to queue SaveLoad
01:19:31 Scheduling new unfirm job:054031

01:19:42 Done Scheduling job:054031 sending job to queue SaveLoad
01:19:43 Scheduling new unfirm job:002628-1-7
01:20:03 Done Scheduling job:002628-1-7 sending job to queue SaveLoad
01:20:03 Scheduling new unfirm job:002628-1-1

01:20:24 Done Scheduling job:002628-1-1 sending job to queue SaveLoad
01:20:24 Scheduling new unfirm job:054022
01:20:28 The job is currently scheduled to finish 4/25/2022. It will not meet its required date of 12/31/2021 as  the Company doesn’t allow scheduling in the past.
01:20:28 Done Scheduling job:054022 sending job to queue SaveLoad
01:20:28 Scheduling new unfirm job:003077-1-2

01:20:49 Done Scheduling job:003077-1-2 sending job to queue SaveLoad
01:20:49 Scheduling new unfirm job:054100
01:21:09 Done Scheduling job:054100 sending job to queue SaveLoad
01:21:09 Scheduling new unfirm job:002628-1-8

01:21:30 Done Scheduling job:002628-1-8 sending job to queue SaveLoad
01:21:30 Scheduling new unfirm job:053952

01:21:51 Done Scheduling job:053952 sending job to queue SaveLoad
01:21:51 Scheduling new unfirm job:003084-1-1

01:22:22 Done Scheduling job:003084-1-1 sending job to queue SaveLoad
01:22:22 Scheduling new unfirm job:003208-1-1

01:22:51 Done Scheduling job:003208-1-1 sending job to queue SaveLoad
01:22:51 Scheduling new unfirm job:F-054273

01:23:11 Done Scheduling job:F-054273 sending job to queue SaveLoad
01:23:11 Scheduling new unfirm job:002075-11-1

01:23:40 Done Scheduling job:002075-11-1 sending job to queue SaveLoad
01:23:40 Scheduling new unfirm job:F-055997
01:24:00 Done Scheduling job:F-055997 sending job to queue SaveLoad
01:24:00 Scheduling new unfirm job:051684
01:24:04 The job is currently scheduled to finish 12/15/2021. It will not meet its required date of 12/31/2020 as  the Company doesn’t allow scheduling in the past.
01:24:04 Done Scheduling job:051684 sending job to queue SaveLoad
01:24:04 Scheduling new unfirm job:054892

01:24:21 Done Scheduling job:054892 sending job to queue SaveLoad
01:24:21 Scheduling new unfirm job:054221

01:24:42 Done Scheduling job:054221 sending job to queue SaveLoad
01:24:42 Scheduling new unfirm job:F-054274
01:25:02 Done Scheduling job:F-054274 sending job to queue SaveLoad
01:25:02 Scheduling new unfirm job:002628-1-6

01:25:13 Done Scheduling job:002628-1-6 sending job to queue SaveLoad
01:25:13 Scheduling new unfirm job:055009
01:25:34 Done Scheduling job:055009 sending job to queue SaveLoad
01:25:34 Scheduling new unfirm job:054718

01:25:54 Done Scheduling job:054718 sending job to queue SaveLoad
01:25:54 Scheduling new unfirm job:056212

01:26:15 Done Scheduling job:056212 sending job to queue SaveLoad
01:26:15 Scheduling new unfirm job:003144-1-1

01:26:44 Done Scheduling job:003144-1-1 sending job to queue SaveLoad
01:26:44 Scheduling new unfirm job:002793-1-1

01:29:01 Done Scheduling job:002793-1-1 sending job to queue SaveLoad
01:29:01 Scheduling new unfirm job:055828

01:29:22 Done Scheduling job:055828 sending job to queue SaveLoad
01:29:22 Scheduling new unfirm job:002287-1-4

01:29:43 Done Scheduling job:002287-1-4 sending job to queue SaveLoad
01:29:43 Scheduling new unfirm job:002867-6-1
01:30:00 Done Scheduling job:002867-6-1 sending job to queue SaveLoad
01:30:00 Scheduling new unfirm job:003045-1-1

01:30:17 Done Scheduling job:003045-1-1 sending job to queue SaveLoad
01:30:17 Scheduling new unfirm job:055765
01:30:26 Done Scheduling job:055765 sending job to queue SaveLoad
01:30:26 Scheduling new unfirm job:002949-1-5

01:30:43 Done Scheduling job:002949-1-5 sending job to queue SaveLoad
01:30:43 Scheduling new unfirm job:003131-1-1
01:31:00 Done Scheduling job:003131-1-1 sending job to queue SaveLoad
01:31:00 Scheduling new unfirm job:003172-1-1
01:31:09 Done Scheduling job:003172-1-1 sending job to queue SaveLoad
01:31:09 Scheduling new unfirm job:003230-1-1

01:31:34 Done Scheduling job:003230-1-1 sending job to queue SaveLoad
01:31:34 Scheduling new unfirm job:003229-1-1

01:32:02 Done Scheduling job:003229-1-1 sending job to queue SaveLoad
01:32:02 Scheduling new unfirm job:003048-1-1

01:32:11 Done Scheduling job:003048-1-1 sending job to queue SaveLoad
01:32:11 Scheduling new unfirm job:003044-1-1
01:32:28 Done Scheduling job:003044-1-1 sending job to queue SaveLoad
01:32:28 Scheduling new unfirm job:002562-2-1

01:32:54 Done Scheduling job:002562-2-1 sending job to queue SaveLoad
01:32:54 Scheduling new unfirm job:003127-1-1

01:33:11 Done Scheduling job:003127-1-1 sending job to queue SaveLoad
01:33:11 Scheduling new unfirm job:054684
01:33:28 Done Scheduling job:054684 sending job to queue SaveLoad
01:33:28 Scheduling new unfirm job:003047-1-1

01:33:57 Done Scheduling job:003047-1-1 sending job to queue SaveLoad
01:33:57 Scheduling new unfirm job:055827

01:34:17 Done Scheduling job:055827 sending job to queue SaveLoad
01:34:17 Scheduling new unfirm job:055141
01:34:37 Done Scheduling job:055141 sending job to queue SaveLoad
01:34:37 Scheduling new unfirm job:055008

01:34:46 Done Scheduling job:055008 sending job to queue SaveLoad
01:34:46 Scheduling new unfirm job:002949-1-4
01:35:03 Done Scheduling job:002949-1-4 sending job to queue SaveLoad
01:35:03 Scheduling new unfirm job:003140-1-1

01:35:20 Done Scheduling job:003140-1-1 sending job to queue SaveLoad
01:35:20 Scheduling new unfirm job:003111-2-1

01:35:45 Done Scheduling job:003111-2-1 sending job to queue SaveLoad
01:35:45 Scheduling new unfirm job:002959-3-2

01:36:12 Done Scheduling job:002959-3-2 sending job to queue SaveLoad
01:36:12 Scheduling new unfirm job:003213-1-1
01:36:32 Done Scheduling job:003213-1-1 sending job to queue SaveLoad
01:36:32 Scheduling new unfirm job:003129-1-1

01:36:41 Done Scheduling job:003129-1-1 sending job to queue SaveLoad
01:36:41 Scheduling new unfirm job:003189-2-1
01:37:09 Done Scheduling job:003189-2-1 sending job to queue SaveLoad
01:37:10 Scheduling new unfirm job:003055-1-1

01:37:38 Done Scheduling job:003055-1-1 sending job to queue SaveLoad
01:37:38 Scheduling new unfirm job:055826

01:37:58 Done Scheduling job:055826 sending job to queue SaveLoad
01:37:58 Scheduling new unfirm job:003136-1-1

01:38:15 Done Scheduling job:003136-1-1 sending job to queue SaveLoad
01:38:15 Scheduling new unfirm job:003160-2-1
01:38:32 Done Scheduling job:003160-2-1 sending job to queue SaveLoad
01:38:32 Scheduling new unfirm job:003160-3-1

01:38:49 Done Scheduling job:003160-3-1 sending job to queue SaveLoad
01:38:49 Scheduling new unfirm job:003160-4-1
01:39:06 Done Scheduling job:003160-4-1 sending job to queue SaveLoad
01:39:06 Scheduling new unfirm job:003199-1-1

01:39:31 Done Scheduling job:003199-1-1 sending job to queue SaveLoad
01:39:31 Scheduling new unfirm job:003156-1-1

01:39:49 Done Scheduling job:003156-1-1 sending job to queue SaveLoad
01:39:49 Scheduling new unfirm job:002949-1-6
01:40:06 Done Scheduling job:002949-1-6 sending job to queue SaveLoad
01:40:06 Scheduling new unfirm job:002959-4-2

01:40:32 Done Scheduling job:002959-4-2 sending job to queue SaveLoad
01:40:32 Scheduling new unfirm job:002954-1-1

01:41:01 Done Scheduling job:002954-1-1 sending job to queue SaveLoad
01:41:01 Scheduling new unfirm job:F-000000050104

01:41:26 Done Scheduling job:F-000000050104 sending job to queue SaveLoad
01:41:26 Scheduling new unfirm job:002959-3-3

01:41:44 Done Scheduling job:002959-3-3 sending job to queue SaveLoad
01:41:44 Scheduling new unfirm job:002959-4-3
01:42:03 Done Scheduling job:002959-4-3 sending job to queue SaveLoad
01:42:03 Scheduling new unfirm job:003094-1-1

01:42:32 Done Scheduling job:003094-1-1 sending job to queue SaveLoad
01:42:32 Scheduling new unfirm job:003143-2-1

01:42:57 Done Scheduling job:003143-2-1 sending job to queue SaveLoad
01:42:57 Scheduling new unfirm job:003143-3-1

01:43:26 Done Scheduling job:003143-3-1 sending job to queue SaveLoad
01:43:26 Scheduling new unfirm job:003143-5-1

01:43:51 Done Scheduling job:003143-5-1 sending job to queue SaveLoad
01:43:51 Scheduling new unfirm job:003143-6-1

01:44:20 Done Scheduling job:003143-6-1 sending job to queue SaveLoad
01:44:20 Scheduling new unfirm job:003148-1-1

01:44:45 Done Scheduling job:003148-1-1 sending job to queue SaveLoad
01:44:45 Scheduling new unfirm job:003178-1-1

01:45:14 Done Scheduling job:003178-1-1 sending job to queue SaveLoad
01:45:14 Scheduling new unfirm job:002949-1-1
01:45:31 Done Scheduling job:002949-1-1 sending job to queue SaveLoad
01:45:31 Scheduling new unfirm job:055899

01:45:51 Done Scheduling job:055899 sending job to queue SaveLoad
01:45:51 Scheduling new unfirm job:002255-1-6

01:46:15 Done Scheduling job:002255-1-6 sending job to queue SaveLoad
01:46:15 Scheduling new unfirm job:003180-1-1

01:46:43 Done Scheduling job:003180-1-1 sending job to queue SaveLoad
01:46:43 Scheduling new unfirm job:003155-1-1

01:47:12 Done Scheduling job:003155-1-1 sending job to queue SaveLoad
01:47:12 Scheduling new unfirm job:003097-1-1

01:47:41 Done Scheduling job:003097-1-1 sending job to queue SaveLoad
01:47:41 Scheduling new unfirm job:003143-1-1
01:48:09 Done Scheduling job:003143-1-1 sending job to queue SaveLoad
01:48:09 Scheduling new unfirm job:002937-3-1

01:48:38 Done Scheduling job:002937-3-1 sending job to queue SaveLoad
01:48:38 Scheduling new unfirm job:002287-1-5

01:48:59 Done Scheduling job:002287-1-5 sending job to queue SaveLoad
01:48:59 Scheduling new unfirm job:002867-4-1

01:49:27 Done Scheduling job:002867-4-1 sending job to queue SaveLoad
01:49:27 Scheduling new unfirm job:003196-1-1

01:49:56 Done Scheduling job:003196-1-1 sending job to queue SaveLoad
01:49:56 Scheduling new unfirm job:003105-1-1

01:50:17 Done Scheduling job:003105-1-1 sending job to queue SaveLoad
01:50:17 Scheduling new unfirm job:003233-1-1

01:50:57 Done Scheduling job:003233-1-1 sending job to queue SaveLoad
01:50:57 Scheduling new unfirm job:002911-1-1

01:51:26 Done Scheduling job:002911-1-1 sending job to queue SaveLoad
01:51:26 Scheduling new unfirm job:003196-2-1

01:51:54 Done Scheduling job:003196-2-1 sending job to queue SaveLoad
01:51:54 Scheduling new unfirm job:003071-1-1

01:52:23 Done Scheduling job:003071-1-1 sending job to queue SaveLoad
01:52:23 Scheduling new unfirm job:003111-1-1

01:52:43 Done Scheduling job:003111-1-1 sending job to queue SaveLoad
01:52:43 Scheduling new unfirm job:002075-14-1
01:53:03 Done Scheduling job:002075-14-1 sending job to queue SaveLoad
01:53:03 Scheduling new unfirm job:003220-1-1

01:53:32 Done Scheduling job:003220-1-1 sending job to queue SaveLoad
01:53:32 Scheduling new unfirm job:002287-1-3

01:53:53 Done Scheduling job:002287-1-3 sending job to queue SaveLoad
01:53:53 Scheduling new unfirm job:003038-2-1

01:54:22 Done Scheduling job:003038-2-1 sending job to queue SaveLoad
01:54:22 Scheduling new unfirm job:002845-9-1

01:54:50 Done Scheduling job:002845-9-1 sending job to queue SaveLoad
01:54:50 Scheduling new unfirm job:055898

01:55:11 Done Scheduling job:055898 sending job to queue SaveLoad
01:55:11 Scheduling new unfirm job:055006
01:55:31 Done Scheduling job:055006 sending job to queue SaveLoad
01:55:31 Scheduling new unfirm job:002716-1-1

01:56:00 Done Scheduling job:002716-1-1 sending job to queue SaveLoad
01:56:00 Scheduling new unfirm job:056164

01:56:20 Done Scheduling job:056164 sending job to queue SaveLoad
01:56:20 Scheduling new unfirm job:003192-1-1

01:56:49 Done Scheduling job:003192-1-1 sending job to queue SaveLoad
01:56:49 Scheduling new unfirm job:003157-1-1
01:57:09 Done Scheduling job:003157-1-1 sending job to queue SaveLoad
01:57:09 Scheduling new unfirm job:003210-1-1

01:57:29 Done Scheduling job:003210-1-1 sending job to queue SaveLoad
01:57:29 Scheduling new unfirm job:003201-1-1

01:57:50 Done Scheduling job:003201-1-1 sending job to queue SaveLoad
01:57:50 Scheduling new unfirm job:002931-1-1

01:58:11 Done Scheduling job:002931-1-1 sending job to queue SaveLoad
01:58:11 Scheduling new unfirm job:003103-1-1
01:58:36 Done Scheduling job:003103-1-1 sending job to queue SaveLoad
01:58:36 Scheduling new unfirm job:055897

01:58:57 Done Scheduling job:055897 sending job to queue SaveLoad
01:58:57 Scheduling new unfirm job:003145-1-1

01:59:27 Done Scheduling job:003145-1-1 sending job to queue SaveLoad
01:59:27 Scheduling new unfirm job:003157-2-1

01:59:49 Done Scheduling job:003157-2-1 sending job to queue SaveLoad
01:59:49 Scheduling new unfirm job:003194-1-1

02:00:21 Done Scheduling job:003194-1-1 sending job to queue SaveLoad
02:00:21 Scheduling new unfirm job:002287-1-6

02:00:42 Done Scheduling job:002287-1-6 sending job to queue SaveLoad
02:00:42 Scheduling new unfirm job:003108-1-1

02:01:13 Done Scheduling job:003108-1-1 sending job to queue SaveLoad
02:01:13 Scheduling new unfirm job:055822
02:01:35 Done Scheduling job:055822 sending job to queue SaveLoad
02:01:35 Scheduling new unfirm job:003221-1-1

02:02:06 Done Scheduling job:003221-1-1 sending job to queue SaveLoad
02:02:06 Scheduling new unfirm job:002287-1-2

02:02:27 Done Scheduling job:002287-1-2 sending job to queue SaveLoad
02:02:27 Scheduling new unfirm job:002287-1-1

02:02:49 Done Scheduling job:002287-1-1 sending job to queue SaveLoad
02:02:49 Scheduling new unfirm job:003076-1-1

02:03:19 Done Scheduling job:003076-1-1 sending job to queue SaveLoad
02:03:19 Scheduling new unfirm job:003159-1-1
02:03:36 Done Scheduling job:003159-1-1 sending job to queue SaveLoad
02:03:36 Scheduling new unfirm job:003147-1-1

02:04:07 Done Scheduling job:003147-1-1 sending job to queue SaveLoad
02:04:07 Scheduling new unfirm job:003217-1-1

02:04:38 Done Scheduling job:003217-1-1 sending job to queue SaveLoad
02:04:38 Scheduling new unfirm job:003219-1-1

02:04:41 The job is currently scheduled to finish 11/4/2021. It will not meet its required date of 9/14/2021 as  the Company doesn’t allow scheduling in the past.
02:04:41 Done Scheduling job:003219-1-1 sending job to queue SaveLoad
02:04:41 Scheduling new unfirm job:003200-1-1

02:05:12 Done Scheduling job:003200-1-1 sending job to queue SaveLoad
02:05:12 Scheduling new unfirm job:U-000000000132
02:05:15 The job is currently scheduled to finish 10/19/2021. It will not meet its required date of 9/28/2021 as  the Company doesn’t allow scheduling in the past.
02:05:15 Done Scheduling job:U-000000000132 sending job to queue SaveLoad
02:05:15 Scheduling new unfirm job:050213
02:05:19 The job is currently scheduled to finish 10/21/2021. It will not meet its required date of 12/31/2020 as  the Company doesn’t allow scheduling in the past.
02:05:19 Done Scheduling job:050213 sending job to queue SaveLoad
02:05:19 Scheduling new unfirm job:003239-1-1

02:05:50 Done Scheduling job:003239-1-1 sending job to queue SaveLoad
02:05:50 Scheduling new unfirm job:055663
02:05:50 The job is currently scheduled to finish 10/26/2021. It will not meet its required date of 9/10/2021 as  the Company doesn’t allow scheduling in the past.
02:05:50 Done Scheduling job:055663 sending job to queue SaveLoad
02:05:50 Scheduling new unfirm job:003203-1-1

02:06:43 Done Scheduling job:003203-1-1 sending job to queue SaveLoad
02:06:43 Scheduling new unfirm job:003228-1-1

02:07:13 Done Scheduling job:003228-1-1 sending job to queue SaveLoad
02:07:13 Scheduling new unfirm job:003061-1-1
02:07:17 The job is currently scheduled to finish 10/27/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
02:07:17 Done Scheduling job:003061-1-1 sending job to queue SaveLoad
02:07:17 Scheduling new unfirm job:F-055144
02:07:17 The job is currently scheduled to finish 10/11/2021. It will not meet its required date of 5/31/2021 as  the Company doesn’t allow scheduling in the past.
02:07:17 Done Scheduling job:F-055144 sending job to queue SaveLoad
02:07:17 Scheduling new unfirm job:003042-1-1

02:07:48 Done Scheduling job:003042-1-1 sending job to queue SaveLoad
02:07:48 Scheduling new unfirm job:003143-4-1

02:08:18 Done Scheduling job:003143-4-1 sending job to queue SaveLoad
02:08:18 Scheduling new unfirm job:054928
02:08:19 The job is currently scheduled to finish 10/14/2021. It will not meet its required date of 10/1/2021 as  the Company doesn’t allow scheduling in the past.
02:08:19 Done Scheduling job:054928 sending job to queue SaveLoad
02:08:19 Scheduling new unfirm job:052767
02:08:19 The job is currently scheduled to finish 12/16/2021. It will not meet its required date of 12/18/2020 as  the Company doesn’t allow scheduling in the past.
02:08:19 Done Scheduling job:052767 sending job to queue SaveLoad
02:08:19 Scheduling new unfirm job:F-054841
02:08:19 The job is currently scheduled to finish 10/8/2021. It will not meet its required date of 5/9/2021 as  the Company doesn’t allow scheduling in the past.
02:08:19 Done Scheduling job:F-054841 sending job to queue SaveLoad
02:08:19 Scheduling new unfirm job:003063-1-1

02:08:52 Done Scheduling job:003063-1-1 sending job to queue SaveLoad
02:08:52 Scheduling new unfirm job:003177-1-1

02:09:22 Done Scheduling job:003177-1-1 sending job to queue SaveLoad
02:09:22 Scheduling new unfirm job:003126-1-1
02:09:26 The job is currently scheduled to finish 10/21/2021. It will not meet its required date of 9/24/2021 as  the Company doesn’t allow scheduling in the past.
02:09:26 Done Scheduling job:003126-1-1 sending job to queue SaveLoad

03:02:49 Scheduling new unfirm job:003212-1-1

03:03:18 Done Scheduling job:003212-1-1 sending job to queue SaveLoad
03:03:18 Scheduling new unfirm job:M056270
03:03:21 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 8/25/2021 as  the Company doesn’t allow scheduling in the past.
03:03:21 Done Scheduling job:M056270 sending job to queue SaveLoad
03:03:21 Scheduling new unfirm job:M056276
03:03:25 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 8/25/2021 as  the Company doesn’t allow scheduling in the past.
03:03:25 Done Scheduling job:M056276 sending job to queue SaveLoad
03:03:25 Scheduling new unfirm job:M056277
03:03:28 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 8/25/2021 as  the Company doesn’t allow scheduling in the past.
03:03:28 Done Scheduling job:M056277 sending job to queue SaveLoad
03:03:28 Scheduling new unfirm job:003175-2-1
03:03:32 The job is currently scheduled to finish 10/27/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:32 Done Scheduling job:003175-2-1 sending job to queue SaveLoad
03:03:32 Scheduling new unfirm job:003175-3-1
03:03:35 The job is currently scheduled to finish 10/27/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:35 Done Scheduling job:003175-3-1 sending job to queue SaveLoad
03:03:35 Scheduling new unfirm job:003175-4-1
03:03:39 The job is currently scheduled to finish 10/22/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:39 Done Scheduling job:003175-4-1 sending job to queue SaveLoad
03:03:39 Scheduling new unfirm job:003175-5-1

03:03:42 The job is currently scheduled to finish 10/28/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:42 Done Scheduling job:003175-5-1 sending job to queue SaveLoad
03:03:42 Scheduling new unfirm job:003196-3-1
03:03:46 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:46 Done Scheduling job:003196-3-1 sending job to queue SaveLoad
03:03:46 Scheduling new unfirm job:003240-1-1
03:03:49 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/26/2021 as  the Company doesn’t allow scheduling in the past.
03:03:49 Done Scheduling job:003240-1-1 sending job to queue SaveLoad
03:03:49 Scheduling new unfirm job:003171-1-1

03:04:14 Done Scheduling job:003171-1-1 sending job to queue SaveLoad
03:04:14 Scheduling new unfirm job:M054395
03:04:18 The job is currently scheduled to finish 9/29/2021.  It will not meet its required date of 8/27/2021 due to a purchasing constraint  { 5231 / 1 / 1 } 
03:04:18 Done Scheduling job:M054395 sending job to queue SaveLoad
03:04:18 Scheduling new unfirm job:M055928
03:04:21 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:21 Done Scheduling job:M055928 sending job to queue SaveLoad
03:04:21 Scheduling new unfirm job:M056007
03:04:24 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:24 Done Scheduling job:M056007 sending job to queue SaveLoad
03:04:24 Scheduling new unfirm job:M056076
03:04:28 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:28 Done Scheduling job:M056076 sending job to queue SaveLoad
03:04:28 Scheduling new unfirm job:M056169
03:04:31 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:31 Done Scheduling job:M056169 sending job to queue SaveLoad
03:04:31 Scheduling new unfirm job:M056186
03:04:34 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:34 Done Scheduling job:M056186 sending job to queue SaveLoad
03:04:34 Scheduling new unfirm job:M056244
03:04:38 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:38 Done Scheduling job:M056244 sending job to queue SaveLoad
03:04:38 Scheduling new unfirm job:M056256

03:04:41 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:41 Done Scheduling job:M056256 sending job to queue SaveLoad
03:04:41 Scheduling new unfirm job:M056260
03:04:45 The job is currently scheduled to finish 10/1/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:45 Done Scheduling job:M056260 sending job to queue SaveLoad
03:04:45 Scheduling new unfirm job:M056262
03:04:48 The job is currently scheduled to finish 10/1/2021. It will not meet its required date of 8/27/2021 as  the Company doesn’t allow scheduling in the past.
03:04:48 Done Scheduling job:M056262 sending job to queue SaveLoad
03:04:48 Scheduling new unfirm job:003189-1-1
03:04:54 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 8/30/2021 as  the Company doesn’t allow scheduling in the past.
03:04:54 Done Scheduling job:003189-1-1 sending job to queue SaveLoad
03:04:54 Scheduling new unfirm job:003189-3-1
03:04:59 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 8/30/2021 as  the Company doesn’t allow scheduling in the past.
03:04:59 Done Scheduling job:003189-3-1 sending job to queue SaveLoad
03:04:59 Scheduling new unfirm job:003189-4-1
03:05:04 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 8/30/2021 as  the Company doesn’t allow scheduling in the past.
03:05:04 Done Scheduling job:003189-4-1 sending job to queue SaveLoad
03:05:04 Scheduling new unfirm job:003189-5-1
03:05:10 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 8/30/2021 as  the Company doesn’t allow scheduling in the past.
03:05:10 Done Scheduling job:003189-5-1 sending job to queue SaveLoad
03:05:10 Scheduling new unfirm job:003189-6-1

03:05:15 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 8/30/2021 as  the Company doesn’t allow scheduling in the past.
03:05:15 Done Scheduling job:003189-6-1 sending job to queue SaveLoad
03:05:15 Scheduling new unfirm job:003191-1-1
03:05:20 The job is currently scheduled to finish 10/18/2021. It will not meet its required date of 8/31/2021 as  the Company doesn’t allow scheduling in the past.
03:05:20 Done Scheduling job:003191-1-1 sending job to queue SaveLoad
03:05:20 Scheduling new unfirm job:003191-2-1
03:05:25 The job is currently scheduled to finish 10/14/2021. It will not meet its required date of 8/31/2021 as  the Company doesn’t allow scheduling in the past.
03:05:25 Done Scheduling job:003191-2-1 sending job to queue SaveLoad
03:05:25 Scheduling new unfirm job:003152-2-1
03:05:29 The job is currently scheduled to finish 9/29/2021.  It will not meet its required date of 9/3/2021 due to a purchasing constraint  { 6234 / 2 / 1 } 
03:05:29 Done Scheduling job:003152-2-1 sending job to queue SaveLoad
03:05:29 Scheduling new unfirm job:003152-3-1
03:05:32 The job is currently scheduled to finish 9/29/2021.  It will not meet its required date of 9/3/2021 due to a purchasing constraint  { 6327 / 1 / 1 } 
03:05:32 Done Scheduling job:003152-3-1 sending job to queue SaveLoad
03:05:32 Scheduling new unfirm job:003226-1-1

03:05:53 Done Scheduling job:003226-1-1 sending job to queue SaveLoad
03:05:53 Scheduling new unfirm job:056092
03:05:56 The job is currently scheduled to finish 9/30/2021. It will not meet its required date of 9/3/2021 as  the Company doesn’t allow scheduling in the past.
03:05:56 Done Scheduling job:056092 sending job to queue SaveLoad
03:05:56 Scheduling new unfirm job:M055961
03:05:59 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 9/3/2021 as  the Company doesn’t allow scheduling in the past.
03:05:59 Done Scheduling job:M055961 sending job to queue SaveLoad
03:06:00 Scheduling new unfirm job:M056307
03:06:03 The job is currently scheduled to finish 9/29/2021.  It will not meet its required date of 9/3/2021 due to a purchasing constraint  { 6454 / 1 / 1 } 
03:06:03 Done Scheduling job:M056307 sending job to queue SaveLoad
03:06:03 Scheduling new unfirm job:003083-1-1

03:06:28 Done Scheduling job:003083-1-1 sending job to queue SaveLoad
03:06:28 Scheduling new unfirm job:F-056309
03:06:32 The job is currently scheduled to finish 12/15/2021. It will not meet its required date of 9/20/2021 as  the Company doesn’t allow scheduling in the past.
03:06:32 Done Scheduling job:F-056309 sending job to queue SaveLoad
03:06:32 Scheduling new unfirm job:002940-1-1
03:06:33 The job is currently scheduled to finish 9/29/2021. It will not meet its required date of 9/27/2021 as  the Company doesn’t allow scheduling in the past.
03:06:33 Done Scheduling job:002940-1-1 sending job to queue SaveLoad
03:06:33 Scheduling new unfirm job:003198-3-1
03:06:38 The job is currently scheduled to finish 12/23/2021. It will not meet its required date of 9/28/2021 as  the Company doesn’t allow scheduling in the past.
03:06:38 Done Scheduling job:003198-3-1 sending job to queue SaveLoad
03:06:38 Scheduling new unfirm job:003009-1-1

03:06:55 Done Scheduling job:003009-1-1 sending job to queue SaveLoad
03:06:55 Scheduling new unfirm job:M055362
03:06:59 Done Scheduling job:M055362 sending job to queue SaveLoad
03:06:59 Scheduling new unfirm job:003089-1-1

03:07:18 Done Scheduling job:003089-1-1 sending job to queue SaveLoad
03:07:18 Scheduling new unfirm job:002825-1-1
03:07:37 Done Scheduling job:002825-1-1 sending job to queue SaveLoad
03:07:37 Scheduling new unfirm job:003085-1-1

03:07:49 Done Scheduling job:003085-1-1 sending job to queue SaveLoad
03:07:49 Scheduling new unfirm job:003102-1-1
03:08:08 Done Scheduling job:003102-1-1 sending job to queue SaveLoad
03:08:08 Scheduling new unfirm job:003170-1-1

03:08:19 Done Scheduling job:003170-1-1 sending job to queue SaveLoad
03:08:19 Scheduling new unfirm job:002897-1-1

03:08:41 Done Scheduling job:002897-1-1 sending job to queue SaveLoad
03:08:41 Scheduling new unfirm job:002897-2-1
03:09:04 Done Scheduling job:002897-2-1 sending job to queue SaveLoad
03:09:04 Scheduling new unfirm job:002897-3-1

03:09:28 Done Scheduling job:002897-3-1 sending job to queue SaveLoad
03:09:28 Scheduling new unfirm job:002897-4-1

03:09:49 Done Scheduling job:002897-4-1 sending job to queue SaveLoad
03:09:49 Scheduling new unfirm job:002897-5-1
03:10:10 Done Scheduling job:002897-5-1 sending job to queue SaveLoad
03:10:10 Scheduling new unfirm job:002897-6-1

03:10:32 Done Scheduling job:002897-6-1 sending job to queue SaveLoad
03:10:32 Scheduling new unfirm job:002897-7-1

03:11:20 Done Scheduling job:002897-7-1 sending job to queue SaveLoad
03:11:20 Scheduling new unfirm job:003089-1-2
03:11:31 Done Scheduling job:003089-1-2 sending job to queue SaveLoad
03:11:31 Scheduling new unfirm job:003077-1-4

03:11:44 Done Scheduling job:003077-1-4 sending job to queue SaveLoad
03:11:44 Scheduling new unfirm job:003164-1-1
03:11:54 Done Scheduling job:003164-1-1 sending job to queue SaveLoad
03:11:54 Scheduling new unfirm job:003168-1-1

03:12:12 Done Scheduling job:003168-1-1 sending job to queue SaveLoad
03:12:12 Scheduling new unfirm job:003057-1-1
03:12:29 Done Scheduling job:003057-1-1 sending job to queue SaveLoad
03:12:29 Scheduling new unfirm job:003077-1-5
03:12:38 Done Scheduling job:003077-1-5 sending job to queue SaveLoad
03:12:38 Scheduling new unfirm job:M055944

03:12:42 The job is currently scheduled to finish 10/4/2021. It will not meet its required date of 9/30/2021 as  the Company doesn’t allow scheduling in the past.
03:12:42 Done Scheduling job:M055944 sending job to queue SaveLoad
03:12:42 Scheduling new unfirm job:003040-1-1
03:12:42 The job is currently scheduled to finish 12/27/2021. It will not meet its required date of 10/7/2021 as  the Company doesn’t allow scheduling in the past.
03:12:42 Done Scheduling job:003040-1-1 sending job to queue SaveLoad
03:12:42 Scheduling new unfirm job:003183-1-1
03:13:02 Done Scheduling job:003183-1-1 sending job to queue SaveLoad
03:13:02 Scheduling new unfirm job:003113-2-1

03:13:43 Done Scheduling job:003113-2-1 sending job to queue SaveLoad
03:13:43 Scheduling new unfirm job:003146-1-1

03:14:15 Done Scheduling job:003146-1-1 sending job to queue SaveLoad
03:14:15 Scheduling new unfirm job:055549
03:14:37 Done Scheduling job:055549 sending job to queue SaveLoad
03:14:37 Scheduling new unfirm job:002732-2-1

03:15:18 Done Scheduling job:002732-2-1 sending job to queue SaveLoad
03:15:18 Scheduling new unfirm job:003186-1-1
03:15:39 Done Scheduling job:003186-1-1 sending job to queue SaveLoad
03:15:39 Scheduling new unfirm job:F-000000050108
03:15:40 The job is currently scheduled to finish 10/18/2021. It will not meet its required date of 10/1/2021 as  the Company doesn’t allow scheduling in the past.
03:15:40 Done Scheduling job:F-000000050108 sending job to queue SaveLoad
03:15:40 Scheduling new unfirm job:003186-2-1

03:16:01 Done Scheduling job:003186-2-1 sending job to queue SaveLoad
03:16:01 Scheduling new unfirm job:003014-1-1

03:16:24 Done Scheduling job:003014-1-1 sending job to queue SaveLoad
03:16:24 Scheduling new unfirm job:002823-1-1

03:17:06 Done Scheduling job:002823-1-1 sending job to queue SaveLoad
03:17:06 Scheduling new unfirm job:003222-1-1

03:17:27 Done Scheduling job:003222-1-1 sending job to queue SaveLoad
03:17:27 Scheduling new unfirm job:003113-1-1

03:17:58 Done Scheduling job:003113-1-1 sending job to queue SaveLoad
03:17:58 Scheduling new unfirm job:003077-1-3
03:18:10 Done Scheduling job:003077-1-3 sending job to queue SaveLoad
03:18:10 Scheduling new unfirm job:003161-1-1

03:18:52 Done Scheduling job:003161-1-1 sending job to queue SaveLoad
03:18:52 Scheduling new unfirm job:003179-1-1

03:19:34 Done Scheduling job:003179-1-1 sending job to queue SaveLoad
03:19:34 Scheduling new unfirm job:003179-2-1

03:20:15 Done Scheduling job:003179-2-1 sending job to queue SaveLoad
03:20:15 Scheduling new unfirm job:F-056313

03:21:40 Scheduling new unfirm job:003077-1-6
03:21:40 Done Scheduling job:003077-1-6 sending job to queue SaveLoad

03:21:44 Done Scheduling Jobs.  Wait Time: 00h:00m:00s:000ms, Jobs: 977

03:22:44 Saving Scheduling Load...
03:22:44 Saving load for job:003020-1-1

03:25:03 Saving load for multi job: 003077-1-6
03:25:03 Done saving load for job:003077-1-6

03:25:45 MRP process 1 done.  Total Non Scheduling Time = 00h:01m:26s:399ms. Scheduled Jobs: 977 Deleted Jobs: 0 Save Load Jobs: 958

Looking through them, I saw that the jobhead is not available to save for multi-jobs and a good bit of jobs that will not finish on time (Part of that is I am using my test database which is a month old), but I didn’t see anything to help figure out why it is scheduling the same resource for numerous jobs at the same time.

I also did see where it says there is no resource available to schedule operation 20 of assembly 1 on job 003214-1-1 but again, doesn’t seem like that would cause other jobs to overschedule.

Also, I removed part of the second log (just lines that were the same as others) due to the fact that I was past the character count for a post.