Too late to easily fix once received/inspect-passed.
Re-Inspect your PO received/inspection-passed inventory o/h & fail 11 pc. DMR disposition (fail - to remove o/h from sys) to some meaningful reason code that simply means a receiving count error. Generate a debit memo for the 11 pc & have the buyer call the vendor so they know what is going on.
Rob
Re-Inspect your PO received/inspection-passed inventory o/h & fail 11 pc. DMR disposition (fail - to remove o/h from sys) to some meaningful reason code that simply means a receiving count error. Generate a debit memo for the 11 pc & have the buyer call the vendor so they know what is going on.
Rob
--- On Mon, 12/29/08, Vic Drecchio <vic.drecchio@...> wrote:
From: Vic Drecchio <vic.drecchio@...>
Subject: [Vantage] Reciept Error
To: vantage@yahoogroups.com
Date: Monday, December 29, 2008, 10:48 AM
Good morning,
I need to find out if there is a way to change a quantity that was
received on a PO after it has gone through inspection. Here is our
scenario:
PO 19 came in on 12/23/08. The PO requires 100, the vendor shipped a
partial qty of 60. We received a qty of 71 by mistake. It went through
the inspection process and into the shop. It wasn't until later in the
day that we realized the receiving error. So, now we show that the PO is
short 29, when it is really short 40.
What's the best method to resolve this?
Thank you in advance.
Vic
[Non-text portions of this message have been removed]