Scheduling sub assembly

Hi

I have an issue about subassembly.

I have a Manufacture part with a revision method with a subassembly manufactured part.

I am trying to make the sub-assembly a day before the parent part (even if both parts will fit in the same day schedule).

I don’t want to create a fake Operation for that and I tried Move Time and it does not work. Look like the fact that it’s a Sub assembly the Move Time wont work.

Any ideas …

have you tried Receive Time, for the subassembly manufactured part, scheduling engine should pick this up

Hi Al

We did the test. The receive time in the sub part don’t just move the Sub Part, but also the operation of the parent part

so basically it will move the entire job x days before du End date

Philippe