Vantage 8.03.404 - MRP and job creation

Thanks Rob. I will give this a try.

--- In vantage@yahoogroups.com, Robert Brown <robertb_versa@...>
wrote:
>
> On the Part Plant Detail tab, check off "Process MRP', in the
MRP planning section (per your example): set the Min Lot Size to 15,
the Multiple to 15, the Max to 30; and, in the Inventory section,
set Min On-Hand to 15, Max On-Hand to 30, and check of "ReOrder to
max".
>  
> Probably a good idea to make these item Stock/Non-Phantom as well
as you will consistenly have inv asset to account for at
any given time.
>  
> Rob Brown 
>
> --- On Tue, 5/27/08, c.chest c.chest@... wrote:
>
> From: c.chest c.chest@...
> Subject: [Vantage] Vantage 8.03.404 - MRP and job creation
> To: vantage@yahoogroups.com
> Date: Tuesday, May 27, 2008, 11:20 AM
>
>
>
>
>
>
> Is there a way to have Vantage plan to a reorder point? We are
> setting up a psuedo Kanban (can't use the Vantage Kanban because
we
> are using lot control). If the min is 15 and the max is 30, and I
> only want to produce in quantities of 15, if I have 30 pcs in
> inventory and then get demand for 5 pcs...I don't want to see a
> suggestion to open a job for 15 pcs. This will put me over max
> inventory level. I wouldn't want to see a suggestion until I
reached
> or went below min. Is anyone doing anything like this?
>
>
>
>
>
>
>
>
>
>
>
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
Is there a way to have Vantage plan to a reorder point? We are
setting up a psuedo Kanban (can't use the Vantage Kanban because we
are using lot control). If the min is 15 and the max is 30, and I
only want to produce in quantities of 15, if I have 30 pcs in
inventory and then get demand for 5 pcs...I don't want to see a
suggestion to open a job for 15 pcs. This will put me over max
inventory level. I wouldn't want to see a suggestion until I reached
or went below min. Is anyone doing anything like this?
On the Part Plant Detail tab, check off "Process MRP', in the MRP planning section (per your example): set the Min Lot Size to 15, the Multiple to 15, the Max to 30; and, in the Inventory section, set Min On-Hand to 15, Max On-Hand to 30, and check of "ReOrder to max".
 
Probably a good idea to make these item Stock/Non-Phantom as well as you will consistenly have inv asset to account for at any given time.
 
Rob Brown 

--- On Tue, 5/27/08, c.chest <c.chest@...> wrote:

From: c.chest <c.chest@...>
Subject: [Vantage] Vantage 8.03.404 - MRP and job creation
To: vantage@yahoogroups.com
Date: Tuesday, May 27, 2008, 11:20 AM






Is there a way to have Vantage plan to a reorder point? We are
setting up a psuedo Kanban (can't use the Vantage Kanban because we
are using lot control). If the min is 15 and the max is 30, and I
only want to produce in quantities of 15, if I have 30 pcs in
inventory and then get demand for 5 pcs...I don't want to see a
suggestion to open a job for 15 pcs. This will put me over max
inventory level. I wouldn't want to see a suggestion until I reached
or went below min. Is anyone doing anything like this?


















[Non-text portions of this message have been removed]