When I added an Inspection Plan to the part and carried that part over to a Job. I can see the plan, but nowhere in MES is it letting me add the data to the plan. When I add it to the Operation, MES sees it just fine. I have a manufactured part, that i want to a add a 10 % sampling for calibration. Nothing in MES gives me that option.
Did you ever figure it out? I’m in the same boat as you are. I added the inspection plan to the operation, instead of the part, but nothing happens after I’m using the MES and clocking in that operation
It’s been a while, but I think the trigger is ‘end activity’ with a reportable quantity.
1 Like
Nothing happened on my end, but thanks for the feedback anyways.