Hi, I’ve done some searching but can’t seem to find what I’m looking for. I need to get a total of all estimated labor based on a BOM. I’ve tried using some CTE queries I have, but the total labor does not seem to be adding up. I am using the PartOpr table to get the estimated setup and estimated production hours. Anyone out there have a BAQ like this they wouldn’t mind sharing?
Related topics
| Topic | Replies | Views | Activity | |
|---|---|---|---|---|
| Thousands of LabHours Entries from BAQ | 12 | 683 | July 15, 2021 | |
| Materials/Operation/Resource Cost: Report-BAQ-Dashboard | 4 | 842 | September 29, 2023 | |
| BOM indented level BAQ | 1 | 411 | October 6, 2023 | |
| BAQ "subquery" help | 20 | 1129 | May 6, 2025 | |
| Quote Cost BAQ / Report | 9 | 1265 | May 5, 2025 |