Hi,
In Epicor 9.04.502B, I have created global currency in one company say companyA. But I cannot link the same currency in another company say companyB.
I have started sonic management console.I checked the status of sonic Adapter in Open edge Progress, it is started.
For CompanyA, I did multicompany setup and multisystem setup for sonic.
And for other companyB, i did the same setup.
I have checked the multicompany serverlog file. There its showing the following message:
"04/14/09 11:31:52 (EPICOR:9001) Multi-Company Process - Sonic Session Failure
04/14/09 11:31:52 (EPICOR:9001) Multi-Company Process - Completed
04/14/09 11:32:52 (EPICOR:9001) Multi-Company Process - Processing
04/14/09 11:32:52 (EPICOR:9001) Multi-Company Process - Starting Sonic Session (TCP://epicor.automechgroup.net:2506)"
Kindly advice me what is the reason for sonic session failure?
Did i miss any steps.?
Thank you in advance &
Kind Regards,
Deepa.M
[Non-text portions of this message have been removed]
In Epicor 9.04.502B, I have created global currency in one company say companyA. But I cannot link the same currency in another company say companyB.
I have started sonic management console.I checked the status of sonic Adapter in Open edge Progress, it is started.
For CompanyA, I did multicompany setup and multisystem setup for sonic.
And for other companyB, i did the same setup.
I have checked the multicompany serverlog file. There its showing the following message:
"04/14/09 11:31:52 (EPICOR:9001) Multi-Company Process - Sonic Session Failure
04/14/09 11:31:52 (EPICOR:9001) Multi-Company Process - Completed
04/14/09 11:32:52 (EPICOR:9001) Multi-Company Process - Processing
04/14/09 11:32:52 (EPICOR:9001) Multi-Company Process - Starting Sonic Session (TCP://epicor.automechgroup.net:2506)"
Kindly advice me what is the reason for sonic session failure?
Did i miss any steps.?
Thank you in advance &
Kind Regards,
Deepa.M