Job Splitting, Information Changed

Thanks Steve,

Appreciate your input.

Steve

-----Original Message-----
From: Steve Lewis [SMTP:slewis@...]
Sent: Monday, October 09, 2000 5:37 PM
To: vantage@egroups.com
Subject: RE: [Vantage] Job Splitting, Information Changed

Steve - I ran into the same problem several months back, and
Vantage could
not give me an answer. You will find that the same thing will
happen if you
change the build qty in any way. We have a built in scrap
factor, which will
drive the lower ass'y to a larger qty to cover any scrap that we
encounter
along the way. But when I change the build qty for a job, I
found that the
scrap rate goes to zero, and I ended up with nothing to cover
scrap parts.
So far, the only thing that I have been able to do is MANUALLY
input an
overrun factor on the jobs that I change. This seems ridiculous
to me, but
Vantage offered no support. I believe it is still an open issue
for them.

-----Original Message-----
From: Steve Wirtz [mailto:SWirtz@...]
Sent: Monday, October 09, 2000 11:07 AM
To: 'vantage@egroups.com'
Subject: [Vantage] Job Splitting, Information Changed


I just ran across a result of a job split which is disturbing as
I don't
think we did anything to cause this situation to happen.

Instead of delivering all the product for a customer next month,
the
customer requested we deliver the product over eight months with
shipments every two months. We had issued most purchase orders
against
the original job number. We split the job into three additional
jobs,
making four jobs with four equal deliveries. But the three new
jobs had
quantity differences at the lower level from the original jobs.
Everything seemed OK, but starting at the second level of the
bill of
material the quantity per parent reverted back to 1 per parent.
Has
anyone else encountered this?

Was:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy.
2
1 8
3 0122-40 Major Component 3
1 16
4 0122-51 Major Subassy.
4
1 8
5 0122-01 detail part
5 4 2

Result on Split Jobs:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy.
2
1 1
3 0122-40 Major Component 3
1 1
4 0122-51 Major Subassy.
4
1 1
5 0122-01 detail part
5 4 1



I just tried this in Vantage training and verified that when the
job is
split the Sub-Assembly quantity/parent was again changed back to
1.
Does anybody know why?

Steve


-------------------------- eGroups Sponsor

We no longer allow attachments to files. To access/share Report
Files, please go to the following link:
http://www.egroups.com/files/vantage/
(Note: If this link does not work for you the first time you
try it, go to www.egroups.com, login and be sure to save your password,
choose My Groups, choose Vantage, then choose Files. If you save the
password, the link above will work the next time you try it.)
I just ran across a result of a job split which is disturbing as I don't
think we did anything to cause this situation to happen.

Instead of delivering all the product for a customer next month, the
customer requested we deliver the product over eight months with
shipments every two months. We had issued most purchase orders against
the original job number. We split the job into three additional jobs,
making four jobs with four equal deliveries. But the three new jobs had
quantity differences at the lower level from the original jobs.
Everything seemed OK, but starting at the second level of the bill of
material the quantity per parent reverted back to 1 per parent. Has
anyone else encountered this?

Was:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy. 2
1 8
3 0122-40 Major Component 3
1 16
4 0122-51 Major Subassy. 4
1 8
5 0122-01 detail part
5 4 2

Result on Split Jobs:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy. 2
1 1
3 0122-40 Major Component 3
1 1
4 0122-51 Major Subassy. 4
1 1
5 0122-01 detail part
5 4 1



I just tried this in Vantage training and verified that when the job is
split the Sub-Assembly quantity/parent was again changed back to 1.
Does anybody know why?

Steve
Steve - I ran into the same problem several months back, and Vantage could
not give me an answer. You will find that the same thing will happen if you
change the build qty in any way. We have a built in scrap factor, which will
drive the lower ass'y to a larger qty to cover any scrap that we encounter
along the way. But when I change the build qty for a job, I found that the
scrap rate goes to zero, and I ended up with nothing to cover scrap parts.
So far, the only thing that I have been able to do is MANUALLY input an
overrun factor on the jobs that I change. This seems ridiculous to me, but
Vantage offered no support. I believe it is still an open issue for them.

-----Original Message-----
From: Steve Wirtz [mailto:SWirtz@...]
Sent: Monday, October 09, 2000 11:07 AM
To: 'vantage@egroups.com'
Subject: [Vantage] Job Splitting, Information Changed


I just ran across a result of a job split which is disturbing as I don't
think we did anything to cause this situation to happen.

Instead of delivering all the product for a customer next month, the
customer requested we deliver the product over eight months with
shipments every two months. We had issued most purchase orders against
the original job number. We split the job into three additional jobs,
making four jobs with four equal deliveries. But the three new jobs had
quantity differences at the lower level from the original jobs.
Everything seemed OK, but starting at the second level of the bill of
material the quantity per parent reverted back to 1 per parent. Has
anyone else encountered this?

Was:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy. 2
1 8
3 0122-40 Major Component 3
1 16
4 0122-51 Major Subassy. 4
1 8
5 0122-01 detail part
5 4 2

Result on Split Jobs:

Level Part No. Description
Assembly No. Parent Assembly QTY/Parent
0 0122 Top Assy
0 None None
1 0122-90 Pack-out
1 0 1
2 0122-50 Major Subassy. 2
1 1
3 0122-40 Major Component 3
1 1
4 0122-51 Major Subassy. 4
1 1
5 0122-01 detail part
5 4 1



I just tried this in Vantage training and verified that when the job is
split the Sub-Assembly quantity/parent was again changed back to 1.
Does anybody know why?

Steve