Labor Hours and Plant Shop Floor

yes

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
progress92000
Sent: Thursday, October 27, 2005 12:47 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Labor Hours and Plant Shop Floor

and it is based on hundredths of an hour?

--- In vantage@yahoogroups.com, sarah.vareschi@n... wrote:
>
> The Labor hours will get divided among all the jobs he is clocked
into. The
> burden hours depend on how you have it set-up in the work center
master
> file.
>
> -----Original Message-----
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On
Behalf Of
> progress92000
> Sent: Thursday, October 27, 2005 12:25 PM
> To: vantage@yahoogroups.com
> Subject: [Vantage] Labor Hours and Plant Shop Floor
>
> Hi Group,
>
> How the system calculate the labor hours per job? Multiple Jobs?
>
> I got one employee clockin at 8:44AM and clockout at 9:41AM so it
is
> 0.57 min but on the Operation showing laborhrs = 0.11
>
> I know he clockin multiple jobs at the time. Does it matter? How
does
> it calculate?
>
> Any idea?
>
> Thank you,
>
>
>
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You
must have
> already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report
Builder and
> Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/links
> Yahoo! Groups Links
>







Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
Yahoo! Groups Links
Hi Group,

How the system calculate the labor hours per job? Multiple Jobs?

I got one employee clockin at 8:44AM and clockout at 9:41AM so it is
0.57 min but on the Operation showing laborhrs = 0.11

I know he clockin multiple jobs at the time. Does it matter? How does
it calculate?

Any idea?

Thank you,
The Labor hours will get divided among all the jobs he is clocked into. The
burden hours depend on how you have it set-up in the work center master
file.

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
progress92000
Sent: Thursday, October 27, 2005 12:25 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Labor Hours and Plant Shop Floor

Hi Group,

How the system calculate the labor hours per job? Multiple Jobs?

I got one employee clockin at 8:44AM and clockout at 9:41AM so it is
0.57 min but on the Operation showing laborhrs = 0.11

I know he clockin multiple jobs at the time. Does it matter? How does
it calculate?

Any idea?

Thank you,






Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
Yahoo! Groups Links
and it is based on hundredths of an hour?

--- In vantage@yahoogroups.com, sarah.vareschi@n... wrote:
>
> The Labor hours will get divided among all the jobs he is clocked
into. The
> burden hours depend on how you have it set-up in the work center
master
> file.
>
> -----Original Message-----
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On
Behalf Of
> progress92000
> Sent: Thursday, October 27, 2005 12:25 PM
> To: vantage@yahoogroups.com
> Subject: [Vantage] Labor Hours and Plant Shop Floor
>
> Hi Group,
>
> How the system calculate the labor hours per job? Multiple Jobs?
>
> I got one employee clockin at 8:44AM and clockout at 9:41AM so it
is
> 0.57 min but on the Operation showing laborhrs = 0.11
>
> I know he clockin multiple jobs at the time. Does it matter? How
does
> it calculate?
>
> Any idea?
>
> Thank you,
>
>
>
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You
must have
> already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report
Builder and
> Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/links
> Yahoo! Groups Links
>