Labor Reporting Resource / Scheduling Resources

Doing some DMT updates and have been unable to change the Scheduling Resource value within either Part Revisions or Jobs. Running thru the steps manually works just fine but via DMT, haven’t had any luck getting these values to change. Manually, the changing of the Resource Group value on the Scheduling Resources seems to change the Labor Reporting Resource > Production value automatically upon changing so I’m not sure what I’m missing during a DMT run to update these values.
Any ideas?

DMT’s can be tricky in that it doesnt’ really tell you ALL of the mandatory columns required to change things. I would see if including a bit more in the DMT file fixes it. I’ve not tried changing the scheduled resources on anything but the Operations master.